HomeMy WebLinkAbout23-48 Change Order No. 1 2023 Paving Project Asphalt Specialties Company 04-26-2023RESOLUTION NO.23-48
A RESOLUTION OF THE BOARD OF TRUSTEES OF THE TOWN OF
FIRESTONE, COLORADO APPROVING CHANGE ORDER NO.1 OF THE
2023 PAVING PROJECT AGREEMENT BETWEEN THE TOWN OF
FIRESTONE AND ASPHALT SPECLALTIES COMPANY INC.
WHEREAS, the Town of Firestone ("Town") contracted with Asphalt Specialties
Company Inc. ("Asphalt Specialties") for the Town's 2023 Paving Project; and
WHEREAS, after Asphalt Specialties completed the edge milling section of Summerset
Ave. and Eastview St. it determined with Town staff s agreement that the bottom mat of the
remining asphalt is not suitable for paving but must be completely removed and replaced.
NOW, THEREFORE, BE IT RESOLVED BY THE BOARD OF TRUSTEES OF THE
TOWN OF FIRESTONE, COLORADO:
Change Order No. 1 of the 2023 Paving Project Contract between the Town of Firestone
and Asphalt Specialties Company Inc. is approved in substantially the same form as the copy
attached hereto and made a part of this resolution and the Mayor is authorized to execute Change
Order No. 1 on behalf of the Town.
INTRODUCED, READ AND ADOPTED this 26' day of April, 2023.
TO OFF ONE,COLORADO
Drew Alan Peterson, Mayor
ATTEST:
Mi&m4i6a Gonzalez, Deputy Town Clerk
1
Date of Issuance:
2023 Paving Project S2023-9234
ASPHALT SPECIALTIES COMPANY, INC
SECTION 00941
CHANGE ORDER
No. 1
Effective Date: April 17, 2023
Town of Firestone
The Contract Documents are modified as follows upon execution of this Change Order:
Description:
193 SY 6" Removal and replacement of existing asphalt- 66 tons of HMAIGr S)(75)(Pg64-22)with RAP on a section of Summerset Ave
and Eastview St.
Attachments (list documents supporting change):
CHANGE IN CONTRACT PRICE: - CHANGE IN CONTRACT TIMES:
Original Contract Price: Original Contract Times: Working days ❑ Calendar days
Substantial completion (days or date): 60 days
$760,000.00 Ready for final payment (days or date): Upon comoletion
[Increase] [Decrease] from previously approved Change [Increase] [Decrease] from previously approved Change Orders
Orders No. 0 to No. 0: No. 0 to No. 0:
$0.00
Contract Price prior to this Change Order.
$760,000.00
[Increase] of this Change Order.
$10,900.00
Contract Price incorporating this Change Order.
$770,900.00
RECOMMENDED:
By: David Minor, Project Manager
Public Works (Authorized Signature)
Date: 4/20/2023
Substantial completion (days): ]
Ready for final payment (days):
Contract Times prior to this Change Order.
Substantial completion (days or date): 60 days
Ready for final payment (days or date): Upon completion
[Increase] [Decrease] of this Change Order:
Substantial completion (days or date): ++0
Ready for final payment (days or date): +(
Contract Times with all approved Change Orders
Substantial completion (days or date): 60 days
Ready for final payment (days or date): U o
(Older (Aututh(hized Signature) cltyoLI(Authi
Date: Date: / r�