HomeMy WebLinkAboutWANDELL - Flowline Pre-Abandonment Notice - Crestone - 4/17/2025State of Colorado
Energy & Carbon Management Commission
1120 Lincoln Street, Suite 801, Denver, Colorado 80203
Phone: (303) 894-2100 Fax: (303) 894-2109
Off-Location Flowline
FORM
44
Rev
02/20
Document Number:
ECMC RECEPTION
Receive Date:
04/17/2025
The Flowline Report, Form 44, shall be submitted to register, report realignment, report removal from service, provide pre-
abandonment notices, or report abandonment of Off-Location Flowlines, Flowline Systems, Produced Water Transfer Systems, or
Crude Oil Transfer Lines or Systems as required by the 1100 Series Rules. The Form 44 shall also be submitted to register, report
realignment, or report abandonment of Domestic Taps, and to report Grade 1 Gas Leaks from Flowlines per Rules 610 and 906.
404168546
OFF LOCATION FLOWLINE
FLOWLINE ENDPOINT LOCATION IDENTIFICATION
Location ID:336439 Location Type:Production Facilities
Name:WANDELL Number:2N67W/7NENE
County:WELD
Qtr Qtr:NENE Section:7 Township:2N Range:67W Meridian:6
Latitude:40.157860 Longitude:-104.927860
Description of Corrosion Protection
Crestone pipelines are covered in a protective external coating. Flowlines are subject to thorough inspections and
fabrication standards during installation to minimize coating and pipe defects. Crestone maintains a chemical
program to reduce internal corrosion. If a flowline is found to lack integrity, Crestone will investigate, report, and
remediate any spills in accordance with the 900 series rules.
Description of Integrity Management Program
Crestone flowlines are pressure tested prior to placing flowlines into service. Flowlines are tested on an annual
basis in accordance with COGCC 1104 series rules. If a flowline is found to lack integrity, Crestone will
investigate the root cause, as well as report and remediate any spills in accordance with the 900 series rules. All
repairs will be completed in accordance with COGCC 1102 Series rules.
Description of the construction method used for public by-ways, road crossings, sensitive wildlife habitats, sensitive
areas, and natural and manmade watercourses (i.e., open trench, bored and cased, or bored only), if applicable.
N/A
FLOWLINE FACILITY INFORMATION
Flowline Facility ID:473584 Flowline Type:Wellhead Line Action Type:Pre-Abandonment
Notice
OFF LOCATION FLOWLINE REGISTRATION
Equipment at End Point Riser:Separator
ECMC Operator Number:
City:
Company Name:
Address:
10633
CRESTONE PEAK RESOURCES OPERATING LLC
555 17TH STREET SUITE 3700
DENVER Zip:State:80202
Contact Person:Fred Kayser
Phone:(970) 396-4900
CO
Email:fkayser@civiresources.com
Is the Operator a Tier One member of the Utility Notification Center of Colorado (CO811) that participates in Colorado's
One Call notification system?Yes No
Operator Information
Date Run: 4/17/2025 Doc [#404168546]Page 1 of 11
Flowline Start Point Location Identification
Location ID:336439 Location Type:Well Site
Name:WANDELL Number:2N67W/7NENE
County:WELD
Qtr Qtr:NENE Section:7 Township:2N Range:67W Meridian:6
Latitude:40.157860 Longitude:-104.927860
Equipment at Start Point Riser:Well
Flowline Description and Testing
Type of Fluid Transferred:Multiphase Pipe Material:Carbon Steel Max Outer Diameter:(Inches)2.000
Bedding Material:Native Materials Date Construction Completed:03/26/2011
Maximum Anticipated Operating Pressure (PSI):310 Testing PSI:
Test Date:
OFF LOCATION FLOWLINE Pre-Abandonment Notice
Date:05/17/2025
Pre-Abandonment 30-day Notice
Removed per Rule 1105.d.(2)
Abandoned In Place per Rule 1105.d.(2) Exceptions - select all that apply:
A. A surface owner agreement executed by a surface owner allows abandonment in place.
B. The line is subject to the jurisdiction of the federal government, and the relevant federal agency directs
abandonment in place.
Abandoned In Place per Rule 1105.d.(3)
C. The flowline or crude oil transfer line is co-located with other active pipelines or utilities or is in a recorded
right of way.
D. Removal of the line would cause significant damage to natural resources, including wildlife resources, topsoil,
or vegetation.
E. The flowline or crude oil transfer line is in a restricted surface occupancy area or sensitive wildlife habitat.
F. The flowline or crude oil transfer line or a segment of the line crosses or is within 30 feet of a public road,
railroad, bike path, public right of way, utility corridor, or active utility or pipeline crossing.
G. The flowline or crude oil transfer line or a segment of the line crosses or is within 30 feet of or from under a
river, stream, lake, pond, reservoir, wetlands, watercourse, waterway, or spring.
H. The operator demonstrates and quantifies that the removal of the flowline will cause significant emissions of
air pollutants.
Description of Pre-Abandonment Notice:
The flowline serving the WANDELL 6-0-7 (05-123-32467) will be removed in its entirety. Bellholes will be dug on
average every 80 feet and the line pulled. Once the flowline is removed, any areas that need it will be backfilled and
the land surface will be graded.
No Location ID
FLOWLINE FACILITY INFORMATION
Flowline Facility ID:473586 Flowline Type:Wellhead Line Action Type:
OFF LOCATION FLOWLINE REGISTRATION
Equipment at End Point Riser:Separator
Flowline Start Point Location Identification
Location ID:336456 Location Type:Well Site
Date Run: 4/17/2025 Doc [#404168546]Page 2 of 11
Name:WANDELL-62N67W Number:7SWNE
County:WELD
Qtr Qtr:SWNE Section:7 Township:2N Range:67W Meridian:6
Latitude:40.154856 Longitude:-104.930875
Equipment at Start Point Riser:Well
Flowline Description and Testing
Type of Fluid Transferred:Multiphase Pipe Material:Carbon Steel Max Outer Diameter:(Inches)2.000
Bedding Material:Native Materials Date Construction Completed:04/14/1999
Maximum Anticipated Operating Pressure (PSI):320 Testing PSI:
Test Date:
OFF LOCATION FLOWLINE Realignment, Out of Service, Pre-Abandonment Notice, or Abandonment
Verification
Date:10/22/2022
Description of Realignment, Out of Service, Pre-Abandonment Notice, or
Abandonment Verification:
The flowline (12319581_FL) servicing the Wandell 32-7 (05-123-19581) is now out of service as per rule 1102.O.(2).
The most recent successful pressure test was conducted 6/6/2021.
No Location ID
FLOWLINE FACILITY INFORMATION
Flowline Facility ID:473583 Flowline Type:Wellhead Line Action Type:
OFF LOCATION FLOWLINE REGISTRATION
Equipment at End Point Riser:Separator
Flowline Start Point Location Identification
Location ID:336456 Location Type:Well Site
Name:WANDELL-62N67W Number:7SWNE
County:WELD
Qtr Qtr:SWNE Section:7 Township:2N Range:67W Meridian:6
Latitude:40.154856 Longitude:-104.930875
Equipment at Start Point Riser:Well
Flowline Description and Testing
Type of Fluid Transferred:Multiphase Pipe Material:Carbon Steel Max Outer Diameter:(Inches)2.000
Bedding Material:Native Materials Date Construction Completed:12/24/2002
Maximum Anticipated Operating Pressure (PSI):320 Testing PSI:
Test Date:
OFF LOCATION FLOWLINE Realignment, Out of Service, Pre-Abandonment Notice, or Abandonment
Verification
Date:10/22/2022
Description of Realignment, Out of Service, Pre-Abandonment Notice, or
Abandonment Verification:
The flowline (1232113812321166_FL) servicing the Wandell 33-7, Wandell 43-7 (05-123-21138, 05-123-21166) is
now out of service as per rule 1102.O.(2). The most recent successful pressure test was conducted 1/24/2021.
No Location ID
Date Run: 4/17/2025 Doc [#404168546]Page 3 of 11
FLOWLINE FACILITY INFORMATION
Flowline Facility ID:473581 Flowline Type:Wellhead Line Action Type:Pre-Abandonment
Notice
OFF LOCATION FLOWLINE REGISTRATION
Equipment at End Point Riser:Separator
Flowline Start Point Location Identification
Location ID:336439 Location Type:Well Site
Name:WANDELL Number:2N67W/7NENE
County:WELD
Qtr Qtr:NENE Section:7 Township:2N Range:67W Meridian:6
Latitude:40.157860 Longitude:-104.927860
Equipment at Start Point Riser:Well
Flowline Description and Testing
Type of Fluid Transferred:Multiphase Pipe Material:Carbon Steel Max Outer Diameter:(Inches)2.000
Bedding Material:Date Construction Completed:04/19/2008
Maximum Anticipated Operating Pressure (PSI):Testing PSI:
Test Date:
OFF LOCATION FLOWLINE Pre-Abandonment Notice
Date:05/17/2025
Pre-Abandonment 30-day Notice
Removed per Rule 1105.d.(2)
Abandoned In Place per Rule 1105.d.(2) Exceptions - select all that apply:
A. A surface owner agreement executed by a surface owner allows abandonment in place.
B. The line is subject to the jurisdiction of the federal government, and the relevant federal agency directs
abandonment in place.
Abandoned In Place per Rule 1105.d.(3)
C. The flowline or crude oil transfer line is co-located with other active pipelines or utilities or is in a recorded
right of way.
D. Removal of the line would cause significant damage to natural resources, including wildlife resources, topsoil,
or vegetation.
E. The flowline or crude oil transfer line is in a restricted surface occupancy area or sensitive wildlife habitat.
F. The flowline or crude oil transfer line or a segment of the line crosses or is within 30 feet of a public road,
railroad, bike path, public right of way, utility corridor, or active utility or pipeline crossing.
G. The flowline or crude oil transfer line or a segment of the line crosses or is within 30 feet of or from under a
river, stream, lake, pond, reservoir, wetlands, watercourse, waterway, or spring.
H. The operator demonstrates and quantifies that the removal of the flowline will cause significant emissions of
air pollutants.
Description of Pre-Abandonment Notice:
The flowline serving the WANDELL 41-7 (05-123-21070) will be removed in its entirety. Bellholes will be dug on
average every 80 feet and the line pulled. Once the flowline is removed, any areas that need it will be backfilled and
the land surface will be graded.
No Location ID
Date Run: 4/17/2025 Doc [#404168546]Page 4 of 11
FLOWLINE FACILITY INFORMATION
Flowline Facility ID:473580 Flowline Type:Wellhead Line Action Type:Pre-Abandonment
Notice
OFF LOCATION FLOWLINE REGISTRATION
Equipment at End Point Riser:Separator
Flowline Start Point Location Identification
Location ID:336439 Location Type:Well Site
Name:WANDELL Number:2N67W/7NENE
County:WELD
Qtr Qtr:NENE Section:7 Township:2N Range:67W Meridian:6
Latitude:40.157860 Longitude:-104.927860
Equipment at Start Point Riser:Well
Flowline Description and Testing
Type of Fluid Transferred:Multiphase Pipe Material:Carbon Steel Max Outer Diameter:(Inches)2.000
Bedding Material:Native Materials Date Construction Completed:03/19/2011
Maximum Anticipated Operating Pressure (PSI):260 Testing PSI:
Test Date:
OFF LOCATION FLOWLINE Pre-Abandonment Notice
Date:05/17/2025
Pre-Abandonment 30-day Notice
Removed per Rule 1105.d.(2)
Abandoned In Place per Rule 1105.d.(2) Exceptions - select all that apply:
A. A surface owner agreement executed by a surface owner allows abandonment in place.
B. The line is subject to the jurisdiction of the federal government, and the relevant federal agency directs
abandonment in place.
Abandoned In Place per Rule 1105.d.(3)
C. The flowline or crude oil transfer line is co-located with other active pipelines or utilities or is in a recorded
right of way.
D. Removal of the line would cause significant damage to natural resources, including wildlife resources, topsoil,
or vegetation.
E. The flowline or crude oil transfer line is in a restricted surface occupancy area or sensitive wildlife habitat.
F. The flowline or crude oil transfer line or a segment of the line crosses or is within 30 feet of a public road,
railroad, bike path, public right of way, utility corridor, or active utility or pipeline crossing.
G. The flowline or crude oil transfer line or a segment of the line crosses or is within 30 feet of or from under a
river, stream, lake, pond, reservoir, wetlands, watercourse, waterway, or spring.
H. The operator demonstrates and quantifies that the removal of the flowline will cause significant emissions of
air pollutants.
Description of Pre-Abandonment Notice:
The flowline serving the WANDELL 8-2-7 (05-123-32471) will be removed in its entirety. Bellholes will be dug on
average every 80 feet and the line pulled. Once the flowline is removed, any areas that need it will be backfilled and
the land surface will be graded.
No Location ID
Date Run: 4/17/2025 Doc [#404168546]Page 5 of 11
FLOWLINE FACILITY INFORMATION
Flowline Facility ID:473578 Flowline Type:Wellhead Line Action Type:Pre-Abandonment
Notice
OFF LOCATION FLOWLINE REGISTRATION
Equipment at End Point Riser:Separator
Flowline Start Point Location Identification
Location ID:336439 Location Type:Well Site
Name:WANDELL Number:2N67W/7NENE
County:WELD
Qtr Qtr:NENE Section:7 Township:2N Range:67W Meridian:6
Latitude:40.157860 Longitude:-104.927860
Equipment at Start Point Riser:Well
Flowline Description and Testing
Type of Fluid Transferred:Multiphase Pipe Material:Carbon Steel Max Outer Diameter:(Inches)2.000
Bedding Material:Native Materials Date Construction Completed:03/08/2011
Maximum Anticipated Operating Pressure (PSI):320 Testing PSI:
Test Date:
OFF LOCATION FLOWLINE Pre-Abandonment Notice
Date:05/17/2025
Pre-Abandonment 30-day Notice
Removed per Rule 1105.d.(2)
Abandoned In Place per Rule 1105.d.(2) Exceptions - select all that apply:
A. A surface owner agreement executed by a surface owner allows abandonment in place.
B. The line is subject to the jurisdiction of the federal government, and the relevant federal agency directs
abandonment in place.
Abandoned In Place per Rule 1105.d.(3)
C. The flowline or crude oil transfer line is co-located with other active pipelines or utilities or is in a recorded
right of way.
D. Removal of the line would cause significant damage to natural resources, including wildlife resources, topsoil,
or vegetation.
E. The flowline or crude oil transfer line is in a restricted surface occupancy area or sensitive wildlife habitat.
F. The flowline or crude oil transfer line or a segment of the line crosses or is within 30 feet of a public road,
railroad, bike path, public right of way, utility corridor, or active utility or pipeline crossing.
G. The flowline or crude oil transfer line or a segment of the line crosses or is within 30 feet of or from under a
river, stream, lake, pond, reservoir, wetlands, watercourse, waterway, or spring.
H. The operator demonstrates and quantifies that the removal of the flowline will cause significant emissions of
air pollutants.
Description of Pre-Abandonment Notice:
The flowline serving the WANDELL 8-4-7 (05-123-32472) will be removed in its entirety. Bellholes will be dug on
average every 80 feet and the line pulled. Once the flowline is removed, any areas that need it will be backfilled and
the land surface will be graded.
No Location ID
Date Run: 4/17/2025 Doc [#404168546]Page 6 of 11
FLOWLINE FACILITY INFORMATION
Flowline Facility ID:473585 Flowline Type:Wellhead Line Action Type:Pre-Abandonment
Notice
OFF LOCATION FLOWLINE REGISTRATION
Equipment at End Point Riser:Separator
Flowline Start Point Location Identification
Location ID:336439 Location Type:Well Site
Name:WANDELL Number:2N67W/7NENE
County:WELD
Qtr Qtr:NENE Section:7 Township:2N Range:67W Meridian:6
Latitude:40.157860 Longitude:-104.927860
Equipment at Start Point Riser:Well
Flowline Description and Testing
Type of Fluid Transferred:Multiphase Pipe Material:Carbon Steel Max Outer Diameter:(Inches)2.000
Bedding Material:Date Construction Completed:03/14/2011
Maximum Anticipated Operating Pressure (PSI):Testing PSI:
Test Date:
OFF LOCATION FLOWLINE Pre-Abandonment Notice
Date:05/17/2025
Pre-Abandonment 30-day Notice
Removed per Rule 1105.d.(2)
Abandoned In Place per Rule 1105.d.(2) Exceptions - select all that apply:
A. A surface owner agreement executed by a surface owner allows abandonment in place.
B. The line is subject to the jurisdiction of the federal government, and the relevant federal agency directs
abandonment in place.
Abandoned In Place per Rule 1105.d.(3)
C. The flowline or crude oil transfer line is co-located with other active pipelines or utilities or is in a recorded
right of way.
D. Removal of the line would cause significant damage to natural resources, including wildlife resources, topsoil,
or vegetation.
E. The flowline or crude oil transfer line is in a restricted surface occupancy area or sensitive wildlife habitat.
F. The flowline or crude oil transfer line or a segment of the line crosses or is within 30 feet of a public road,
railroad, bike path, public right of way, utility corridor, or active utility or pipeline crossing.
G. The flowline or crude oil transfer line or a segment of the line crosses or is within 30 feet of or from under a
river, stream, lake, pond, reservoir, wetlands, watercourse, waterway, or spring.
H. The operator demonstrates and quantifies that the removal of the flowline will cause significant emissions of
air pollutants.
Description of Pre-Abandonment Notice:
The flowline serving the WANDEL 6-4-7 (05-123-32469) will be removed in its entirety. Bellholes will be dug on
average every 80 feet and the line pulled. Once the flowline is removed, any areas that need it will be backfilled and
the land surface will be graded.
No Location ID
Date Run: 4/17/2025 Doc [#404168546]Page 7 of 11
FLOWLINE FACILITY INFORMATION
Flowline Facility ID:473579 Flowline Type:Wellhead Line Action Type:Pre-Abandonment
Notice
OFF LOCATION FLOWLINE REGISTRATION
Equipment at End Point Riser:Separator
Flowline Start Point Location Identification
Location ID:336439 Location Type:Well Site
Name:WANDELL Number:2N67W/7NENE
County:WELD
Qtr Qtr:NENE Section:7 Township:2N Range:67W Meridian:6
Latitude:40.157860 Longitude:-104.927860
Equipment at Start Point Riser:Well
Flowline Description and Testing
Type of Fluid Transferred:Multiphase Pipe Material:Carbon Steel Max Outer Diameter:(Inches)2.000
Bedding Material:Date Construction Completed:04/29/2008
Maximum Anticipated Operating Pressure (PSI):Testing PSI:
Test Date:
OFF LOCATION FLOWLINE Pre-Abandonment Notice
Date:05/17/2025
Pre-Abandonment 30-day Notice
Removed per Rule 1105.d.(2)
Abandoned In Place per Rule 1105.d.(2) Exceptions - select all that apply:
A. A surface owner agreement executed by a surface owner allows abandonment in place.
B. The line is subject to the jurisdiction of the federal government, and the relevant federal agency directs
abandonment in place.
Abandoned In Place per Rule 1105.d.(3)
C. The flowline or crude oil transfer line is co-located with other active pipelines or utilities or is in a recorded
right of way.
D. Removal of the line would cause significant damage to natural resources, including wildlife resources, topsoil,
or vegetation.
E. The flowline or crude oil transfer line is in a restricted surface occupancy area or sensitive wildlife habitat.
F. The flowline or crude oil transfer line or a segment of the line crosses or is within 30 feet of a public road,
railroad, bike path, public right of way, utility corridor, or active utility or pipeline crossing.
G. The flowline or crude oil transfer line or a segment of the line crosses or is within 30 feet of or from under a
river, stream, lake, pond, reservoir, wetlands, watercourse, waterway, or spring.
H. The operator demonstrates and quantifies that the removal of the flowline will cause significant emissions of
air pollutants.
Description of Pre-Abandonment Notice:
The flowline serving the WANDELL 31-7 (05-123-20947) will be removed in its entirety. Bellholes will be dug on
average every 80 feet and the line pulled. Once the flowline is removed, any areas that need it will be backfilled and
the land surface will be graded.
No Location ID
Date Run: 4/17/2025 Doc [#404168546]Page 8 of 11
FLOWLINE FACILITY INFORMATION
Flowline Facility ID:473582 Flowline Type:Wellhead Line Action Type:Pre-Abandonment
Notice
OFF LOCATION FLOWLINE REGISTRATION
Equipment at End Point Riser:Separator
Flowline Start Point Location Identification
Location ID:336439 Location Type:Well Site
Name:WANDELL Number:2N67W/7NENE
County:WELD
Qtr Qtr:NENE Section:7 Township:2N Range:67W Meridian:6
Latitude:40.157860 Longitude:-104.927860
Equipment at Start Point Riser:Well
Flowline Description and Testing
Type of Fluid Transferred:Multiphase Pipe Material:Carbon Steel Max Outer Diameter:(Inches)2.000
Bedding Material:Date Construction Completed:04/30/2008
Maximum Anticipated Operating Pressure (PSI):Testing PSI:
Test Date:
OFF LOCATION FLOWLINE Pre-Abandonment Notice
Date:05/17/2025
Pre-Abandonment 30-day Notice
Removed per Rule 1105.d.(2)
Abandoned In Place per Rule 1105.d.(2) Exceptions - select all that apply:
A. A surface owner agreement executed by a surface owner allows abandonment in place.
B. The line is subject to the jurisdiction of the federal government, and the relevant federal agency directs
abandonment in place.
Abandoned In Place per Rule 1105.d.(3)
C. The flowline or crude oil transfer line is co-located with other active pipelines or utilities or is in a recorded
right of way.
D. Removal of the line would cause significant damage to natural resources, including wildlife resources, topsoil,
or vegetation.
E. The flowline or crude oil transfer line is in a restricted surface occupancy area or sensitive wildlife habitat.
F. The flowline or crude oil transfer line or a segment of the line crosses or is within 30 feet of a public road,
railroad, bike path, public right of way, utility corridor, or active utility or pipeline crossing.
G. The flowline or crude oil transfer line or a segment of the line crosses or is within 30 feet of or from under a
river, stream, lake, pond, reservoir, wetlands, watercourse, waterway, or spring.
H. The operator demonstrates and quantifies that the removal of the flowline will cause significant emissions of
air pollutants.
Description of Pre-Abandonment Notice:
The flowline serving the WANDELL 42-7 (05-123-21069) will be removed in its entirety. Bellholes will be dug on
average every 80 feet and the line pulled. Once the flowline is removed, any areas that need it will be backfilled and
the land surface will be graded.
No Location ID
OPERATOR COMMENTS AND SUBMITTAL
Date Run: 4/17/2025 Doc [#404168546]Page 9 of 11
flowlines@civiresources.com
Sr. Regulatory Analyst
04/17/2025
Stephany Olsen
ECMC Approved:Director of ECMC Date:
Based on the information provided herein, this Flowline Report complies with ECMC Rules and applicable orders and is hereby
approved.
Title:
Email:Date:
Print Name:
Signed:
I hereby certify that the statements made in this form are, to the best of my knowledge, true, correct and complete.
Form 44 filed to report PRE-ABANDONMENT notification. The following flowlines will be removed in their entirety:
12332469_FL: services theWANDEL 6-4-7 (05-123-32469)
12320947_FL: services theWANDELL 31-7 (05-123-20947)
12321069_FL: services theWANDELL 42-7 (05-123-21069)
12321070_FL: services theWANDELL 41-7 (05-123-21070)
12332467_FL: services theWANDELL 6-0-7 (05-123-32467)
12332471_FL: services theWANDELL 8-2-7 (05-123-32471)
12332472_FL: services theWANDELL 8-4-7 (05-123-32472)
GIS data has previously been submitted. It is anticipated that abandonment operations will start on or about
05/17/2025
Comments
Date Run: 4/17/2025 Doc [#404168546]Page 10 of 11
ATTACHMENT LIST
Att Doc Num Name
Total Attach: 0 Files
COA Type Description
CONDITIONS OF APPROVAL, IF ANY LIST
User Group Comment Comment Date
Stamp Upon
Approval
Total: 0 comment(s)
General Comments
Date Run: 4/17/2025 Doc [#404168546]Page 11 of 11