HomeMy WebLinkAboutMILLER-62N67W - Flowline Pre-Abandonment Notice - Extraction - 7/20/2025State of Colorado
Energy & Carbon Management Commission
1120 Lincoln Street, Suite 801, Denver, Colorado 80203
Phone: (303) 894-2100 Fax: (303) 894-2109
Off-Location Flowline
FORM
44
Rev
02/20
Document Number:
ECMC RECEPTION
Receive Date:
07/20/2025
The Flowline Report, Form 44, shall be submitted to register, report realignment, report removal from service, provide pre-
abandonment notices, or report abandonment of Off-Location Flowlines, Flowline Systems, Produced Water Transfer Systems, or
Crude Oil Transfer Lines or Systems as required by the 1100 Series Rules. The Form 44 shall also be submitted to register, report
realignment, or report abandonment of Domestic Taps, and to report Grade 1 Gas Leaks from Flowlines per Rules 610 and 906.
404282508
OFF LOCATION FLOWLINE
FLOWLINE ENDPOINT LOCATION IDENTIFICATION
Location ID:317572 Location Type:Production Facilities
Name:MILLER-62N67W Number:17NENE
County:WELD
Qtr Qtr:NENE Section:17 Township:2N Range:67W Meridian:6
Latitude:40.142918 Longitude:-104.908310
Description of Corrosion Protection
Extraction's corrosion procedures are detailed in its Flowline Management SOP. Coating materials will be used
that minimize internal and external corrosion, such as internally coated pipe or stainless steel for water service,
and externally coated FBE on all buried steel pipe. If flowlines are repaired due to corrosion, Extraction will
investigate the failure, promptly respond with the appropriate remedial actions and determine the root cause and
apply corrective actions as necessary. Extraction retains records of its chemical program in the form of Failure
Analysis Reports, records of chemical invoices and chemical delivery.
Description of Integrity Management Program
Extraction's integrity management program is detailed in its Flowline Management SOP, which covers flowline
installation, operation, maintenance, inspection, testing, and repairs. Prior to beginning any project involving
flowlines, Extraction ensures the project plans, flowline installation, flowline maintenance (including repairs) and
all flowline inspection and testing projects meet the requirements of the Flowline Management SOP. All pressure
tests on flowlines will be conducted by an independent, third party qualified to do such testing. Precautions shall
be taken to protect employees and the general public.
Description of the construction method used for public by-ways, road crossings, sensitive wildlife habitats, sensitive
areas, and natural and manmade watercourses (i.e., open trench, bored and cased, or bored only), if applicable.
N/A
FLOWLINE FACILITY INFORMATION
Flowline Facility ID:460531 Flowline Type:Wellhead Line Action Type:
ECMC Operator Number:
City:
Company Name:
Address:
10459
EXTRACTION OIL & GAS INC
555 17TH STREET SUITE 3700
DENVER Zip:State:80202
Contact Person:Fred Kayser
Phone:(970) 396-4900
CO
Email:fkayser@civiresources.com
Is the Operator a Tier One member of the Utility Notification Center of Colorado (CO811) that participates in Colorado's
One Call notification system?Yes No
Operator Information
Date Run: 7/20/2025 Doc [#404282508]Page 1 of 4
OFF LOCATION FLOWLINE REGISTRATION
Equipment at End Point Riser:Separator
Flowline Start Point Location Identification
Location ID:323212 Location Type:Well Site
Name:MILLER 62N67W Number:17NWNE
County:WELD
Qtr Qtr:NWNE Section:17 Township:2N Range:67W Meridian:6
Latitude:40.143845 Longitude:-104.911397
Equipment at Start Point Riser:Well
Flowline Description and Testing
Type of Fluid Transferred:Multiphase Pipe Material:Carbon Steel Max Outer Diameter:(Inches)2.375
Bedding Material:Native Materials Date Construction Completed:10/12/1985
Maximum Anticipated Operating Pressure (PSI):138 Testing PSI:138
Test Date:02/22/2018
OFF LOCATION FLOWLINE Realignment, Out of Service, Pre-Abandonment Notice, or Abandonment
Verification
Date:05/28/2020
Description of Realignment, Out of Service, Pre-Abandonment Notice, or
Abandonment Verification:
Bell holes were dug along the length of the flowline. Flowline was cut and pulled. Approximaetly 965' of 2" steel
flowline (buried +/- 4' deep) was removed. Bell holes were backfilled and land surface graded. The entire flowline
was removed.
No Location ID
FLOWLINE FACILITY INFORMATION
Flowline Facility ID:460530 Flowline Type:Wellhead Line Action Type:Pre-Abandonment
Notice
OFF LOCATION FLOWLINE REGISTRATION
Equipment at End Point Riser:Separator
Flowline Start Point Location Identification
Location ID:318191 Location Type:Well Site
Name:MILLER-62N67W Number:17SWNE
County:WELD
Qtr Qtr:SWNE Section:17 Township:2N Range:67W Meridian:6
Latitude:40.139688 Longitude:-104.910744
Equipment at Start Point Riser:Well
Flowline Description and Testing
Type of Fluid Transferred:Multiphase Pipe Material:Carbon Steel Max Outer Diameter:(Inches)2.375
Bedding Material:Native Materials Date Construction Completed:05/05/1977
Maximum Anticipated Operating Pressure (PSI):98 Testing PSI:98
Test Date:02/22/2018
No Location ID
Date Run: 7/20/2025 Doc [#404282508]Page 2 of 4
OFF LOCATION FLOWLINE Pre-Abandonment Notice
Date:08/19/2025
Pre-Abandonment 30-day Notice
Removed per Rule 1105.d.(2)
Abandoned In Place per Rule 1105.d.(2) Exceptions - select all that apply:
A. A surface owner agreement executed by a surface owner allows abandonment in place.
B. The line is subject to the jurisdiction of the federal government, and the relevant federal agency directs
abandonment in place.
Abandoned In Place per Rule 1105.d.(3)
C. The flowline or crude oil transfer line is co-located with other active pipelines or utilities or is in a recorded
right of way.
D. Removal of the line would cause significant damage to natural resources, including wildlife resources, topsoil,
or vegetation.
E. The flowline or crude oil transfer line is in a restricted surface occupancy area or sensitive wildlife habitat.
F. The flowline or crude oil transfer line or a segment of the line crosses or is within 30 feet of a public road,
railroad, bike path, public right of way, utility corridor, or active utility or pipeline crossing.
G. The flowline or crude oil transfer line or a segment of the line crosses or is within 30 feet of or from under a
river, stream, lake, pond, reservoir, wetlands, watercourse, waterway, or spring.
H. The operator demonstrates and quantifies that the removal of the flowline will cause significant emissions of
air pollutants.
Description of Pre-Abandonment Notice:
The flowline serving the MILLER 32-17 (05-123-08623) will be removed in its entirety. Bellholes will be dug on
average every 80 feet and the line pulled. Once the flowline is removed, any areas that need it will be backfilled and
the land surface will be graded.
flowlines@civiresources.com
Sr. Regulatory Analyst
07/20/2025
Stephany Olsen
ECMC Approved:Director of ECMC Date:
Based on the information provided herein, this Flowline Report complies with ECMC Rules and applicable orders and is hereby
approved.
Title:
Email:Date:
Print Name:
Signed:
I hereby certify that the statements made in this form are, to the best of my knowledge, true, correct and complete.
Form 44 filed to report PRE-ABANDONMENT notification. The following flowline will be removed in its entirety:
12308623FL: services the MILLER 32-17 (05-123-08623)
GIS data has previously been submitted. It is anticipated that abandonment operations will start on or about
08/19/2025
Comments
OPERATOR COMMENTS AND SUBMITTAL
Date Run: 7/20/2025 Doc [#404282508]Page 3 of 4
ATTACHMENT LIST
Att Doc Num Name
Total Attach: 0 Files
COA Type Description
CONDITIONS OF APPROVAL, IF ANY LIST
User Group Comment Comment Date
Stamp Upon
Approval
Total: 0 comment(s)
General Comments
Date Run: 7/20/2025 Doc [#404282508]Page 4 of 4