A RESOLUTION OF THE BOARD OF TRUSTEES OF THE TOWN OF
FIRESTONE, COLORADO, APPROVING CHANGE ORDER N0.3 TO THE
TOWN OF FIRESTONE AND E-Z EXCAVATING INC.'S AGREEMENT FOR THE
INSTALLATION OF A POTABLE WATERLINE AND APPURTENANCES FOR
THE ST. VRAIN WATER TREATMENT PLANT TRANSMISSION PIPELINE
PROJECT
WHEREAS, by adoption of Resolution No. 21-85 the Town of Firestone ("Town") entered
into an agreement with E-Z Excavating Inc., ("EZ") for the installation of a transmission pipeline to
convey water from the St. Wain Water Treatment Plant to the Town's water distribution system; and
WHEREAS, during the performance of its work EZ experienced a number of issues which
required, the redesign of planned crossings after encountering a fiber optic line operated by ATT as
part of a national defense system, modification of the vertical alignment of the pipeline after
encountering two unmarked natural gas pipelines, additional redesign work after discovering a
waterline had been improperly located, and construction of an access gate and appurtenances upon a
portion of the pipeline located on private property; and
WHEREAS, the original Bid Schedule was amended to add an additional air -vac station which
had mistakenly been excluded; and
WHEREAS, all of the above matters constitute a change of conditions beyond the reasonable
expectation of EZ.
NOW, THEREFORE, BE IT RESOLVED BY THE BOARD OF TRUSTEES OF THE
TOWN OF FIRESTONE, COLORADO:
Change Order No. 3 to the Town of Firestone and E-Z Excavating Inc.'s Agreement, for the
installation of a potable waterline and appurtenances, for the St. Vrain Water Treatment Plant
Transmission Pipeline Project is approved in substantially the same form as the copy attached
hereto and made a part of this resolution, and the Mayor is authorized to execute the Change Order
on behalf of the Town.
INTRODUCED, READ, AND ADOPTED this ��c ay
WN OF FIRESTONE, COLORADO
Bixb+bi Sind%Aiar, Mayor
CHANGE ORDER
No.
0
DATE OF ISSUANCE
OWNER'S Contract No.
CONTRACTOR
PROJECT Firestone Reservoir No. 1 Supply and Delivery Infrastructure Project
2/25/2022 EFFECTIVE DATE
Town of Firestone
W2020-9529
HEI Civil
ENGINEER
You are directed to make the following changes in the Contract Documents.
Stantec
Description:
1.) Add Line Item 95-Breaker Testing Tower & Irrigation with units of LS. Unit Price equal to $8,611.75. Total quantity equal to 1-LS.
Resulting line item equal to $8,611,75
2.) Add Line Item 96-Jib Crane Power with units of LS. Unit Price equal to $1,654.22. Total quantity equal to 1-LS. Resulting line item
equal to $1,654,22
3.) Add Line Item 97-Additiona1 Heater Breakers on Tower &Irrigation with units of LS. Unit Price equal to (t7,181.75. Total quantity
equal to 1-LS. Resulting line item equal to $7,181,75
4.) Add Line Item 98-MAU Power and Control Install Irrigation with units of LS. Unit Price equal to $7,412,90. Total quantity equal to 1-
LS. Resulting line item equal to $7,412,90
5.) Add Line Item 99-MAU Power and Control) Install Tower with units of LS. Unit Price equal to $8,176.31. Total quantity equal to 1-LS.
Resulting line item equal to $8,176.31
Attachments: None
CHANGE IN CONTRACT PRICE:
CHANGE IN CONTRACT TIMES:
Original Contract Price
Substantial Completion:
365
$
7,016,948.45
Ready for final payment:
410
days or dates
Net changes from previous Change Orders No.
I to 5
Net changes from previous
Change Orders No. 1 to 5
$
2,498, 066.09
59
days
Contract Price prior to this Change Order
Contract Times prior to this
Change Order
Substantial Completion:
441
$
9,5153014.54
Ready for final payment:
469
Net Increase (decrease) of this Change Order
Net Increase (decrease) of
this Change Order
$
331036093
56
da s
Contract Price with all approved Change Orders
Contract Times with all approved change Orders
Substantial Completion:
497 [March 21, 2022]
$
915481051,47
Ready for final payment:
525 [April 18, 2022]
RECOMMENDED APPRW ED � ACCEPTED
rspvy sy�E.HV.•airc. o�-
G�Mb3n+.oa.:r,asv�mal Wiggins, David ppA°��°°m�°G°=
�UIS �4W .
By: By: By:
Engineer (Authorized Signature) Ow er Authorize gn ure Wntractor (Authorized Signature)
Date: 2/25/2022 Date: /q I'dQa a1 Date: 11.22
This CHANGE ORDER, when executed, constitutes a modification to the CONTRACT. The Contractor accepts this change order as
full compensations for the additional work and any delays to the project caused by this CHANGE ORDER.