HomeMy WebLinkAbout20-85 Hudick Notice of Award Firestone Reservoir No. 1 09-23-2020RESOLUTION NUO AU-5S
A RESOLUTION OF THE BOARD OF TRUSTEES OF THE TOWN OF
FIRESTONE, COLORADO, ISSUING A NOTICE OF AWARD TO HUDICK
EXCAVATING, INC., REGARDING CONSTRUCTION SERVICES FOR THE
FIRESTONE RESERVOIR NO, I SUPPLY AND DELIVERY
INFRASTRUCTURE PROJECT
WHEREAS, the Town of Firestone ("Town") is in need of construction services for the
Firestone Reservoir No. 1 Supply and Delivery Infrastructure Project, which tasks include
construction of two pump stations, irrigation ditch diversions, return flow pipeline and associated
system controls and appurtenances; and
WHEREAS, the Town requested bids for such wort and has selected Hudick Excavating,
he., as the lowest, responsive qualified bidder.
NOW, THEREFORE, BE IT RESOLVED BY THE BOARD OF TRUSTEES OF THE
TOWN OF FIRESTONE, COLORADO,
The Board of Trustees of the Town of Firestone hereby issues allotice of Award to
Hudick Excavating, Inc., for construction services for the Firestone Reservoir No. 1 Supply and
Delivery Infrastructure Project and authorizes the Mayor to execute the Notice of Award,
INTRODUCED, READ AND ADOPTED this dray of , ZULU*
0610 1 were) go]
ATTEST:
Koenig, CMC T
William P�a���lni, Town Attorney
•
j. i9b �:
•s
SECTION 00510
NOTICE OF AWARD
Date: September 14, 2020
Project: Firestone Reservoir No. 1 Supply and Delivery Infrastructure Project
Owner: Town of Firestone Owner's Contract No.. W2020-9529
Contract: Construction Services Engineer's Project No.: 5435-006
Bidder: Hudick Excavating Inc. dba HEI Civil
Bidder's Address: 5460 Montana Vista Way, Castle Rock, CO 80108
You are notified that your Bid dated September 4t—" 2020
for the above Contract has been considered. You are the Successful Bidder and are awarded a Contract
for the Firestone Reservoir No. 1 Supply and Delivery Infrastructure Project,
The Contract Price of your Contract is $ 7 016 948.45
(seven million, sixteen thousand, nine hundred forty-eight dollars and forty-five cents)
Three (3) copies of the proposed Contract Documents (except Drawings) accompany this Notice of
Award.
Two (2) of the Drawings will be delivered separately or otherwise made available to you immediately.
You must comply with the following conditions precedent within ten (10) days of the date you receive this
Notice of Award.
1. Deliver to the Owner three (3) fully executed counterparts of the Contract Documents.
2. Deliver with the executed Contract Documents the Contract security [Bonds] as specified in the
Instructions to Bidders (Article 20), General Conditions (Paragraph 5.01) and Supplementary
Conditions (Paragraph SC-5.01).
Failure to comply with these conditions within the time specified will entitle Owner to consider you in
default, annul this Notice of Award and declare your Bid security forfeited.
Within ten days after you comply with the above conditions, Owner will return to you one fully executed
counterpart of the Contract Documents,
Owner: Town of Firestone
By:
Copy to Engineer
EJCDC C-510 Notice of Award
Prepared by the Engineers Joint Contract Documents Committee and endorsed by the Construction Specifications Institute.
00510-1 of 1