HomeMy WebLinkAbout20-88 Notice of Award Walsh Construction Gould Horizontal Well 09-23-2020RESOLUTION N0.20-88
A RESOLUTION OF THE BOARD OF TRUSTEES OF THE TOWN OF
FIRESTONE, COLORADO, ISSUING A NOTICE OF AWARD TO WALSH
CONSTRUCTION, INC., FOR CONSTRUCTION SERVICES FOR THE GOULD
HORIZONTAL WELL
WHEREAS, as the design work has been completed, the Town of Firestone ("'Town) is in
need of services to construct the Gould Horizontal Well; and
WHEREAS, the Town requested bids for such work and has selected Walsh
Construction, Inc., as the lowest responsive qualified bidder.
NOW, THEREFORE, BE IT RESOLVED BY THE BOARD OF TRUSTEES OF THE
TOWN OF FIRESTONE, COLORADO.
The Board of Trustees of the Town of Firestone hereby issues a Notice of Award to
Walsh Construction, Inc., for construction of the Gould Horizontal Well and authorizes the
Mayor to execute the Notice of Award.
via, l
INTRODUCED, READ AND ADOPTED thisVday of CIL=, 2020.
A
�CM�i:/�1<
7�
ATTEST:
Koenig, C1bIC
' r
a to
�t ;O
� c•, v
`AUNTY, C'O
Clerk
Williail�['�ayashi, Town Attorney
Mayor
LORA
CODO
SECTION 00510
NOTICE OF AWARD
Date: September 23, 2020
Project: Firestone Horizontal Well Project
Owner: Town of Firestone Owner's Contract No.: W2020-9531
Contract: Construction Services Engineer's Project No.: Fire(H-well)
Bidder: Walsh Construction, Inc.
Bidder's Address: 8139 Open View Pt., Loveland, Co. 80537
You are notified that your Bid dated September 11, 2020
for the above Contract has been considered. You are the Successful Bidder and are awarded a Contract
for the Firestone Horizontal Well Proiect,
The Contract Price of your Contract is $ 786,311.00
Electronic copies of the proposed Contract Documents accompany this Notice of Award.
You must comply with the following conditions precedent within ten (10) days of the date you receive this
Notice of Award.
1. Deliver to the Owner three (3) fully executed counterparts of the Contract Documents.
2. Deliver with the executed Contract Documents the Contract security [Bonds] as specified in the
Instructions to Bidders (Article 20), General Conditions (Paragraph 5.01) and Supplementary
Conditions (Paragraph SC-5.01).
Failure to comply with these conditions within the time specified will entitle Owner to consider you in
default, annul this Notice of Award and declare your Bid security forfeited.
Within ten days after you comply with the above conditions,
counterpart of the Contract Documents.
Owner: Town of Firestone
By:
Copy to Engineer
Owner will return to you one fully executed
Cow
EJCDC C-510 Notice of Award
Prepared by the Engineers Joint Contract Documents Committee and endorsed by the Construction Specifications Institute.