HomeMy WebLinkAbout20-05 - Approval of Agreement with McGrane Water Engineering, LLC for Final Design and Construction Engineering ServicesRESOLUTION N"* Lu-uS
A RESOLUTION OF THE BOARD OF TRUSTEES OF THE TOWN OF FIRESTONE,
COLORADO, APPROVING AN AGREEMENT BETWEEN THE TOWN OF
FIRESTONE AND McGRANE WATER ENGINEERING, LLC, FOR FINAL DESIGN
AND CONSTRUCTION ENGINEERING SERVICES
WHEREAS, McGrane Water Engineering LLC, which is clu7ently under contract with
the Town of Firestone ("Town") has completed the site assessment and preliminary design work
for the Gould Horizontal Well Project ("Project") and
WHEREAS the Town is now in need of engineering services for the Project's final
design and construction engineering duties; and
WHEREAS, McGrane Water Engineering LLC is best suited to perform the Project's
I
inal design and construction engineering services in a timely and cost effective manner.
NOW, THEREFORE, BE IT RESOLVED BY THE BOARD OF TRUSTEES OF THE
TOWN OF FIRESTONE, COLORADO:
The Agreement for the Gould Horizontal Well Final Design and Construction
Engineering Services between the Town of Firestone and McGrane Water Engineering, LLC, is
approved in substantially the same form as the copy attached hereto and made a part of this
resolution and the Mayor is authorized to execute the Agreement on behalf of the Town.
WN OF FIRESTONE, COLORADO
bi Sinc%Iar, Mayor
ATTEST:
Jssa Koenig, T
VED AS
Willie �. Hayashi, Town Attorney
Ilh'/�t���
FOR
ENGINEERING SEIaVICES
(Gould Horizontal Well Final Design and Construction Engineering)
THIS AGREEMENT ("Agreement"), is made this th day of 2020, between the
Town of Firestone, a Colorado statutory municipality, hereinafter referred to as 41RESTONE," and
McGrane Water Engineering,LLC, as independent contractor, hereinafter referred to as
"CONSULTANT," and provides as follows:
ARTICLE I
Section 1.1 Services: FIRESTONE retains CONSULTANT, and CONSULTANT agrees
to provide the goods and to perform and complete the work, personal services and/or furnish the
necessary equipment, supplies or materials in accordance with and/or as described in Schedule A,
hereinafter referred to as the "Project." Schedule A is hereby incorporated by reference and made a
part of this Agreement. To the extent that this Agreement and Schedule A conflict, the provisions of
this Agreement shall prevail. Additional goods or services beyond those set out in Schedule A, if
requested, shall be provided only when authorized in writing by FIRESTONE.
Section 1.2 Contract Time: CONSULTANT shall commence work upon direction to
proceed from FIRESTONE and complete the Project on or before December 31, 2021.
Section 1.3 Independent CONSULTANT: CONSULTANT shall at all times control the
means and manner by which CONSULTANT performs the work, subject to FIRESTONE's right to
monitor, evaluate and improve such work. CONSULTANT shall at all times be and act as an
independent CONSULTANT and not as an employee of FIRESTONE.
Section 1.4 Representation of CONSULTANT: CONSULTANT agrees that title to all
goods, materials and equipment covered and paid for under this Agreement will pass to
General Contract for Goods and/or Services (Short Form) (Rev. Jan 2018) Page 1
FIRESTONE, either by incorporation in the Project or upon the receipt of payment by
CONSULTANT, whichever occurs first, free and clear of all liens, claims, security interests or
encumbrances; and that no goods, materials or equipment paid for under this Agreement will have
been acquired by CONSULTANT, or by any other person performing services at the site or
furnishing materials and equipment for the Project, subject to an agreement under which an interest
therein or an encumbrance thereon is retained by the seller or otherwise imposed by CONSULTANT
or such other person.
CONSULTANT represents that it is qualified to assume the responsibilities and render the
services described herein and has all requisite corporate authority and professional licenses required
by law. All professional services shall be performed timely in accordance with generally accepted
professional practices and the level of competency presently maintained by other professionals
providing the same general type of work as set forth in the Scope of Services.
I WDWIM11I.
Section 2.1 Compensation: In consideration of completion of the Project specified
herein by CONSULTANT, FIRESTONE shall pay CONSULTANT (check and initial below as
applicable):
n
A fixed sum of $
® Based upon a time, materials and expenses basis, pursuant to the rate schedule
attached hereto as Schedule A, but in no event shall the total compensation exceed
$ 547,000.00.
❑ As described in Schedule A.
Section 2.2 Pam: FIRESTONE will make payment due to CONSULTANT for
compensation for completed work within thirty (30) days after invoices submitted by
CONSULTANT, which invoice(s) may not be submitted more frequently than monthly. Invoices
shall indicate the basis upon which payment is requested, such as percentage of the Project
completed, or actual time, materials and expenses. FIRESTONE shall submit invoice disputes, if
any, to CONSULTANT within thirty (30) days for resolution by mutual consent.
Section 2.3 Set Off: In addition to any other rights FIRESTONE has under this
Agreement to indemnification or recoupment, CONSULTANT agrees that FIRESTONE is entitled
to set off any amounts it may owe CONSULTANT under this Agreement against such claims for
indemnity or recoupment.
Section 2.4 No Multi -Year Fiscal Obligation. Nothing herein shall constitute a multiple
fiscal year obligation pursuant to Colorado Constitution Article X, Section 20. Notwithstanding any
other provision of this Agreement, FIRESTONE's obligations under this Agreement are subject to
annual appropriation by the Town of FIRESTONE's Board of Trustees. Any failure of the Town
Board of Trustees annually to appropriate adequate monies to finance FIRESTONE's obligations
under this Agreement shall terminate this Agreement at such time as such then -existing
General Contract for Goods and/or Services (Short Form) (Rev. Jan 2018) Page 2
appropriations are to be depleted. Notice shall be given promptly to CONSULTANT of any failure
to appropriate such adequate monies.
Section 2.5 Appropriation: If this is a contract for the design or const>uction, or both the
design and construction of a public works project, the FIRESTONE has appropriated funds equal to
or in excess of the Contract Price.
Section 3.1 Project Performance: In consideration of the compensation provided for in
this Agreement, CONSULTANT agrees to perform or supply the Project, in accordance with
generally accepted standards and practices of the industry Materials incorporated in the Project shall
conform to the specifications, drawings or samples specified or furnished. This Section 3.1 shall
survive any inspection, delivery, acceptance or payment by FIRESTONE.
Section 3.2 Ownership and Use of Documents: (check and initial all that apply)
® (a) The following Sections 3.2(a)(1) and (2) are applicable to design professionals
(architects, engineers, etc.):
(1) The documents prepared by CONSULTANT in connection with the
Project and copies thereof furnished to other parties are for use solely with respect to the Project.
Such documents are not to be used by any other CONSULTANT or subCONSULTANT on other
projects or for additions to this Project outside the scope of the work without the specific written
consent of FIRESTONE and CONSULTANT. Other CONSULTANTS and subCONSULTANTs are
authorized to use and reproduce applicable portions of the documents prepared by CONSULTANT
appropriate to and for use in the execution of their work under this Agreement. All copies made
under this authorization shall bear the statutory copyright notice, if any, shown on the documents
prepared by CONSULTANT.
(2) Notwithstanding the provisions of Section 3.2(a)(1) above,
FIRESTONE may utilize any such documents generated in connection with the Project by
CONSULTANT for other projects, provided that CONSULTANT is not held liable for future project
applications other than the Project described pursuant to this Agreement.
❑ (b) The following Sections 3.2(b)(1) through (3) are applicable to
nonprofessionals (CONSULTANTS, suppliers, etc.):
(1) Any documents prepared by CONSULTANT, and copies thereof
furnished to other parties are for use solely with respect to this Project. They are not to be used by
any other CONSULTANT or subCONSULTANT on other projects or for additions to this Project
outside the scope of the work without the specific written consent of FIRESTONE and
CONSULTANT. Other CONSULTANTS and subCONSULTANTs are authorized to use and
reproduce applicable portions of the documents prepared by the CONSULTANT appropriate to and
for use in the execution of their work under this Agreement. All copies made under this
General Contract for Goods and/or Services (Short Form) (Rev. Jan 2018) Page 3
authorization shall bear the statutory copyright notice, if any, shown on the documents prepared by
CONSULTANT.
(2) CONSULTANT, and any subCONSULTANT or supplier 01 other
person or organization performing or furnishing any work for the Project under a direct or indirect
contract with FIRESTONE (1) shall not have or acquire any title to or ownership rights in any of any
documents (or copies of documents) prepared in connection with the Project by a design professional
and (11) shall not reuse any of such documents or copies for extensions of the Project or any other
project without written consent of FIRESTONE and the design professional and specific written
verification or adaption by the design professional.
(3) Notwithstanding the provisions of Sections 3.2(b)(1) and (2) above,
FIRESTONE may utilize any documents generated in connection with the Project by a design
professional or CONSULTANT for other projects, provided that such design professional and
CONSULTANT are not held liable for future project applications other than the Project described
pursuant to this Agreement. FIRESTONE shall not convey any such documents generated by
CONSULTANT to a third party or use any such documents in a manner adverse to the
CONSULTANT.
Section 3.3 Insurance: CONSULTANT shall, at its own expense, keep in full force
and effect during the term of this Agreement and during the term of any extension or amendment
of this Agreement, insurance as stated below:
(a) Commercial General Liability Insurance with minimum combined single limits of
One Million Dollars and No Cents ($1,000,000.00) for each occurrence and Two Million
Dollars and No Cents ($2,000,000.00) aggregate. The policy shall be applicable to all
premises and operations. The policy shall include coverage for bodily injury, broad form
property damage (including completed operations), personal injury (including coverage for
contractual and employee acts), blanket contractual, independent CONSULTANTs,
products, and completed operations. The policy shall endorse FIRESTONE and its
employees and agents as additional insureds. Additionally, the policy shall provide that such
insurance is primary coverage with respect to work contemplated under this Agreement by
all insureds and additional insureds.
(b) If professional services are provided, Professional Liability Insurance with limits of
One Million Dollars and No Cents ($1,000,000.00) per claim and Two Million Dollars and
No Cents ($2,000,000.00) aggregate. This policy shall remain in force for the period of
design and construction and shall include a discovery period of three years, to commence
upon substantial completion of the Project.
(c) Workers' Compensation Insurance to cover all obligations imposed by applicable
laws for all of CONSULTANT'S employees engaged in the performance of work under this
Agreement, based on statutory limits prescribed by and in accordance with Colorado law. In
the event any services are performed by a subCONSULTANT, CONSULTANT shall require
such subCONSULTANT to provide workers' compensation insurance for its employees.
General Contract For Goods and/or Services (Short Form) (Rev. Jan 2018) Page 4
Cl) Comprehensive Automotive Liability Insurance for the duration of this Agreement
covering all owned, non -owned, and hired vehicles used in connection with the work
performed by or on behalf of CONSULTANT under this Agreement in an amount not less
than Five Hundred Thousand Dollars and No Cents ($500,000.00) combined single limit per
occurrence for bodily injury and property damage.
(e) All of the insurance policies required above shall be written and issued by
responsible companies authorized to do business under the laws of the State of Colorado.
The insurance coverage required shall include those classifications, as listed in standard
liability insurance manuals, which most nearly reflect the operations of CONSULTANT. A
copy of each such policy or certificate shall be provided to FIRESTONE within five (5)
business days of the complete execution of this Agreement and shall be attached to this
Agreement. CONSULTANT shall be responsible for notifying FIRESTONE within five (5)
business days of any material modification to, or cancellation of, these policies during the
term of this Agreement, including but not limited to, any pending or paid claims against the
aggregate amount of the policy, and of any cancellation of coverage for non-payment.
Section 3.4 Colorado Governmental Immunity. The parties hereto understand and
agree that FIRESTONE is relying on, and does not waive or intend to waive by any provision of this
Agreement, the monetary limitations or any other rights, immunities and protections provided it by
the CGIA, C.R.S § 2440401 et seq., as from time to time amended, or otherwise available to
FIRESTONE, its officers or its employees.
Section 3.5 Indemnification: CONSULTANT shall indemnify and hold harmless
FIRESTONE and its officers, officials, and employees from and against liabilities, damages, losses
and expenses, including but not limited to reasonable attorneys' fees, arising out of or resulting from
this Agreement, to the extent that such liability, damage, loss or expense is caused by any negligent,
reckless or intentional act or omission of CONSULTANT or anyone directly employed by
CONSULTANT or anyone for whose acts CONSULTANT may be liable.
Section 3.6 SubCONSULTANT: CONSULTANT shall, as soon as practicable after
executing this Agreement, notify FIRESTONE in writing for FIRESTONE's approval, of any
subCONSULTANTs who may be involved in the Project and the general scope of work to be
performed by each subCONSULTANT. FIRESTONE may, in its reasonable discretion, reject any
proposed subCONSULTANT, in which case CONSULTANT shall either perform such component
or the work itself, or secure a subCONSULTANT acceptable to FIRESTONE.
Section 3.7 Termination for Convenience:
This Agreement may be terminated by FIRESTONE without cause upon seven (7) days
written notice to the CONSULTANT. In the event of termination, FIRESTONE will pay
CONSULTANT for all services satisfactorily performed and for goods provided to date of
termination. If payment is otherwise due in a fixed sum, FIRESTONE will pay CONSULTANT for
the pro rata value of the completed portion of the Project. If, however, CONSULTANT has
substantially or materially breached the standards or terms of this Agreement, FIRESTONE shall
have any remedy or right to set off available at law and equity.
General Contract for Goods and/or Services (Short Form) (Rev. Jan 2018) Page 5
Section 3.8 Binding�Effect/Non-Assi ng ability: FIRESTONE and CONSULTANT each
binds itself, its successors and assigns to the other party to this Agreement with respect to all rights
and obligations under this Agreement. Neither FIRESTONE nor CONSULTANT shall assign or
transfer its interest in, or obligations under, this Agreement without the written consent of the other.
Section 3.9 Compliance with Law: CONSULTANT agrees to perform the work in
compliance with all applicable federal, state, county and city laws, ordinances, rules and regulations,
including without limitation, the preference for Colorado labor as set forth in Article 17 of Title 8
C.R.S.
Section 3.10 Immigration Status Obligations:
a) CONSULTANT certifies, through signature of its author7zed representative executing
this Agreement, that it does not knowingly employ or contract with an illegal alien who will perform
work under the public contract for services and that the CONSULTANT will participate in the
United States Government's &Verify Program or the State of Colorado Department of Labor and
Employment Program ("Department Program") in order to confirm the employment eligibility of all
employees who are newly hired for employment to perform work under the public contract for
services.
b) CONSULTANT shall not:
1) Knowingly employ or contract with an illegal alien to perform work under this
Agreement; or
2) Enter into a contract with a subCONSULTANT that fails to certify to the
CONSULTANT that the subCONSULTANT shall not knowingly employ or contract with an illegal
alien to perform work under the public contract for services.
c) CONSULTANT shall affirm as required by C.R.S. § 8-17.5-102 (c) (II) the
employment eligibility of all employees who are newly hired for employment to perform work under
the public contract for services through participation in either the E-Verify Program or the
Department Program.
d) CONSULTANT is prohibited from using the E-Verify Program or Department
Program procedures to undertake pre -employment screening of job applicants while the public
contract for services is being performed.
e) If CONSULTANT obtains actual knowledge that a subCONSULTANT performing
work under the public contract for• services knowingly employs or contracts with an illegal alien,
CONSULTANT shall be required to:
1) Notify the subCONSULTANT and FIRESTONE within three days that the
CONSULTANT has actual knowledge that the subCONSULTANT is employing or contracting with
an illegal alien$ and
2) Terminate the subcontract with the subCONSULTANT if within three days of
General Contract for Goods and/or Services (Short Form) (Rev. Jan 2018) Page 6
receiving the notice required pursuant to sub -subparagraph k13)k2) the subCONSULTANT does not
stop employing or contracting with the illegal alien; except that the CONSULTANT shall not
terminate the contract with the subCONSULTANT if during such three days the subCONSULTANT
provides information to establish that the subCONSULTANT has not knowingly employed or
contracted with an illegal alien.
f) CONSULTANT shall comply with all rules and regulations and any reasonable
request by the State Department of Labor and Employment made in the course of the Department's
performance of its lawful duties pursuant to C.R.S. 847.5401 et seq., as amended from time to
time.
g) If CONSULTANT violates any of the provisions set forth in this section,
FIRESTONE may terminate the Agreement and CONSULTANT shall be liable for all actual and
consequential damages incurred by FIRESTONE.
Section 3.10 Notice and Communications: Any notice to the parties required under this
Agreement shall be in writing, delivered to the person designated below for the parties at the
indicated address unless otherwise designated in writing. Only mailing by United States mail or
hand delivery shall be utilized. Facsimile and e-mail addresses are provided for convenience only.
FIRESTONE:
Town of Firestone
151 Grant Avenue,
Firestone, CO 80520
Attn: Julie Pasillas
Telephone: 303.531.6 5 8
Facsimile:
E-mail: 1pasillasna,firestoneco.gov
CONSULTANT:
McGrane Water En ing Bering LLC
1669 Apple Valle
Lyons, CO 80540
Attn: Dennis McGrane, PE CPG
lephone: 303.917.1247
Te
Facsimile:
E-Mail:dennisgracgranewater. com
Section 4.1 Protect Materials/ConfidentialitX: FIRESTONE shall provide
CONSULTANT with data, information, reports and other such documentation as may be reasonably
available to FIRESTONE, and reasonably required by CONSULTANT to perform services under
this Agreement. No information shall, unless as required by law, be disclosed by CONSULTANT to
third parties without prior written consent of FIRESTONE. All documents provided by
FIRESTONE to CONSULTANT shall be returned to FIRESTONE. CONSULTANT is authorized
by FIRESTONE to retain copies of such data and materials at CONSULTANT'S EXPENSE.
Section 4.2 Access to Property and Records: FIRESTONE shall provide CONSULTANT
with access to its property as required and necessary to complete the Agreement. To the extent
required by law, FIRESTONE and CONSULTANT agree to make this Agreement and any related
General Contract for Goods and/or Services (Short Form) (Rev. Jan 2018) Page 7
records available for public disclosure pursuant to any open records law, including, without
limitation, the Colorado Open Records Act, C.R.S. §§ 24-72-200.1, et seq. CONSULTANT agrees
to hold FIRESTONE harmless from the disclosure of any records that FIRESTONE reasonably
believes it is legally required to disclose.
Section 4$ FIRESTONE'a Representative; FIRESTONE shall designate, in writing, a
representative who shall have authority to act for FIRESTONE with respect to the services to be
rendered under this Agreement. Such person shall have complete authority to transmit instructions,
receive information, interpret and define FIRESTONE's policies and decisions with respect to
materials, equipment, elements and systems pertinent to CONSULTANT's services.
Section 4.4 Verbal Agreement or Conversation: No verbal agreement or conversation
with any officer, agent or employee of FIRESTONE, either before, during or after the execution of
this Agreement, shall affect or modify any of the terms or obligations herein contained, nor shall
such verbal agreement or conversation entitle CONSULTANT to any additional payment
whatsoever under the terms of this Agreement.
ARTICLE V
MISCELLANEOUS
Section 5.1 Colorado Law: This Agreement is to be governred by the laws of the State of
Colorado. Venue for any litigation shall be in Weld County.
Section 5.2 Amendments; Change Orders: This Agreement may only be amended,
supplemented or modified in a written document signed by both parties (a "Change Order").
Section 5.3 Counterparts. This Agreement may be executed in two or more counterparts,
using manual or facsimile signature, each of which shall be deemed an original and all of which
together shall constitute one and the same document.
Section 5.4. Severability: If any term, covenant, or condition of this Agreement is deemed
by a court of competent jurisdiction to be invalid, void or unenforceable, the remaining provisions of
this Agreement shall be binding upon the parties.
Section 5.5. Entire Agreement: This Agreement constitutes the entire agreement between
the parties and supersedes all other prior and contemporaneous agreements, representations, and
understandings of the parties regarding the subject matter of this Agreement. No supplement,
modification, or amendment of this Agreement shall be binding unless executed in writing by the
parties. No representations or warranties whatever are made by any party to this Agreement except
as specifically set forth in this Agreement or in any instrument delivered pursuant to this Agreement.
Section 5.6. Default/Attorneys Fees: In the event of default of any of the provisions
herein, the defaulting party shall be liable to the non -defaulting party for all reasonable attorney fees,
legal expenses and costs incurred as a result of the default.
Section 5.7. No Waiver: Delays in enforcement or the waiver of any one or more defaults
or breaches of this Agreement by FIRESTONE shall not constitute a waiver of any of the other terms
General Contract for Goods and/or Services (Short Form) (Rev. Jan 2018) Page 8
or obligations of this Agreement.
General Contract for Goods and/or Services (Short Form) (Rev. Jan 2018) Page 9
IN WITNESS WHEREOF, the parties hereto have signed and executed this Agreement the
day first written above,
ATTEST:
APPROVAL AS TO FORM:
I
TOWN OF FIRESTONE
By:
Nat
CONSULTANT
Digitally signed by Dennis McGrane, P.E.,
Den n i sMcG ra n e oN cn=Dennis McGrane, P.E. GP.G,
P.E., C"ij��"G. o=M<GraneWaterEnglneering,OC,ou,
email=dennls@mcgranewatecmm, c=US
By: Date: 2020.01.0813:10:51-07'00'
Name: Dennis McGrane
Title: President
Date:
1 /8/2020
General Contract for Goods and/or Services (Short Form) (Rev, Jan 2018) Page 10
• 'I I'UP1 D
(The following 11 pages are attached to and made a part of the Agreement between the Town of
Firestone and McGrane Water Engineering, LLC )
General Contract for Goods and/or Services (Short Fonn) (Rev. Jan 2018) Page 11
1669 Apple Valley Rd. ,Lyons, CO 80540 ®Office: (303)823-5933, Cell: (303) 917-1247
E-Mail: C.ennkEi arc e €z teP €�. crVia. Website: <v,V%VAI Easee<ttc e€_ i_%� a a _cEa
December 16, 2019
Mr. David Lindsay, President
Colorado Civil Group
5110 Granite St. Suite 200
Loveland, CO 80538
Via email at: dlindsay_(a),cc�inc.com
RE: Proposal —Town of Firestone —Horizontal Well Drilling and Testing
Dear Mr. Lindsay:
At your request, McGrane Water Engineering, LLC (MWE) is providing this proposal to design and
provide construction observation and testing for a 500-ft long horizontal well (H-well) for the Town of
Firestone to be located north of Weld County Rd 26 and east of Colorado Blvd near the Saint Vrain
River. This proposal and opinions of probable costs are based on our current understanding of the
project. Colorado Civil Group (CCG) with act as the Town representative and project manager.
ME will lead the project and design the horizontal well. MWE will subcontract, W
• Groundwater modeling and general engineering support to Miller Groundwater Engineering,
LLC (MGE);
• The vault, pump station and pipeline design to Acuity, Inc. (Acuity); and
• Geotechnical engineering to Cesare, Inc.
Assuming contracting will occur in January 2019, we anticipate the project lasting approximately 13
months and being completed by March 2021. Appendix A includes a Gantt chart that shows live
project phases, anticipated date ranges and how tasks will likely overlap.
Figure 1 shows the existing site, preliminary horizontal well alignment and necessary infrastructure
including:
• A 500 ft long H-well and 500 ft long recharge trench;
• An improved head gate diversion to a single 500 ft long recharge trench;
• A wet -well (vault) with two vertical turbine pumps;
• A simple wood -framed type pump house with power, valves, flow meter, and controls;
• Approximately 600 ft of pipeline to the future water treatment plant site boundary; and
• Approximately four additional monitoring wells around the site.
MWE Horizontal Well, Pump, Pump House and Pipeline Proposal
December 16, 2019
Page 2 of 11
In addition, several geotechnical boreholes will be drilled along the horizontal well alignment.
Figure 1—Horizontal Well Site an
For water discharges during construction dewatering and H-well testing, we propose installing a
temporary, plastic -lined trench to a new 30400t long 124n culvert located under the Varra property
entrance and allow the water to recharge on the east side of Colorado Blvd. A permanent drainage
system will be installed during a later phase of the project.
According to Dave Lindsay (CCG), the immediate goal is to install an H-well that will provide the
Town's planned water treatment plant (WTP) with 220 gallons per minute (gpm) on a year-round
basis and provide a peak summer (June -August) rate of 520 gpm. In the future, when demand
increases, the year-round production rate goal will be approximately 350 gpm with a peak summer
rate of approximately 1,050 gpm. The design will also consider minimizing impacts to the Pelican
Shores Subdivision and Lake located on the west side of Colorado Blvd, as discussed below. It may
be necessary sometime in the future to add additional recharge trenches, or add an additional H-well
to the south, depending on actual year-round operations, H-well performance and future demands.
Computer modeling is a critical component in the system's design, in the interpretation of the start-
up test, and for planning future operations. The modeling will rely heavily on water level data
documented at the site's existing and future monitoring wells. For example, prior groundwater
modeling of the facility indicates that groundwater currently flows through Pelican Shores Lake at a
substantial rate and that the H-well operations will increase that rate of groundwater flow through the
McGrane Water Engineering, LLC
1669 Apple Valley Rd. •Lyons, CO 80540 •Phone: (303) 917-1247
1; Mail: Bennis a mc�,n•auc«ater,com Wcb:[q>://www.nugranewatcrengiuccring.com
MWE Horizontal Well, Pump, Pump House and Pipeline Proposal
December 16, 2019
Page 3 of 11
lake. Ongoing data collection and modeling will be used to monitor and manage that effect.
Similarly, Managed Aquifer Recharge (MAR) will be used to refill the aquifer beneath the site,
which will also cause groundwater levels to rise around the east side of the lake and beneath the
subdivision. Therefore, future site operations will need to include active monitoring and modeling
(especially for the first few years) to guide management decisions such as recharge timing and
recharge amounts.
The suitability of an H-well at the Gould site was initially described in MWE's and MGE's joint
Phase II Groundwater Supply Study (MWE, June 2018). We concluded that a 1,000-ft-long
horizontal well located there could sustain at least 180 gpm year-round without MAR and over 1,000
gpm when MAR is available.
To gain additional confidence in this prediction, we performed two large-scale pumping and recharge
tests in the summer and fall of 2018. We installed additional monitoring wells and two 30M long
recharge trenches in existing agricultural ditches at the Gould site, and then conducted a 60-day
pumping test and 10-day recharge test. We used a computer model of those tests to further evaluate
aquifer conditions, project sustainable yields, and evaluate the relationships between recharge and
various vertical and H-well wellfield configurations. We concluded that two 500-ft long horizontal
wells located on the Gould property could produce approximately 220 gpm year-round and up to
approximately 280 gpm during the summer months (Scenario D). If two 550-ft recharge trenches
were installed and MAR were available between June and September, then the 3-month peak summer
yield projection increased to approximately 1,000 gpm (See Table 2 of MWE draft memo to Dave
Lindsay, December 9, 2018).
The scope of this initial phase of the project is to install a single 500-ft horizontal well and extend one
of the existing recharge trenches to 500 ft. Based on ongoing modeling by MGE, we estimate that a
single 500-ft long H-well can likely achieve the short-term goal of providing 220 gpm year-round
without recharge, and with recharge can achieve the peak summer goal of 520 gpm.
Engineering tasks for each phase are listed below with a basic explanation. Deliverables are marked
with an asterisk (*). Below each subtask, we provide an opinion of probable cost for the primary
construction activities. These cost opinions are also included in the Table 2 cost summary.
Over the past seven months, we:
McGrane Water Engineering, LLC
1669 Apple Valley Rd. •Lyons, CO 80540 •Phone: (303) 917-1247
E-Mail: dcnnisC�mcgrauc��-atcr.com ���cb: Up://«ww,mc�nanc��atcrcngincerin�.com
AWE Horizontal Well, Pump, Pump House and Pipeline Proposal Page 4 of 11
December 16, 2019
• Met with CCG and the Town on April 11, 2019, to discuss the design and construction of
this project;
• Discussed trenching details several times with Saul Sant iesteban (excavator);
• Met and corresponded with Ceasar Inc. (Craig Vaughn) to discuss geotechnical support;
• Met with a horizontal drilling contractor and obtained a well cost estimate,
• Corresponded numerous times with MGE and CCG concerning H-well design (gravel
pack, materials, length, diameter);
• Prepared a preliminary proposal outline* for CCG to review in May 2019;
• Met with MGE and CCG again on October 11, 2019, to discuss project details;
• Prepared draft proposals* dated November 8, and December 2, 2019;
• Met with the Town (CCG), Acuity and MGE on November 1 Vh ;
• Conducted a conference call on December 13, 2019; and
• Prepared this final proposal*.
Horizontal wells are unique. To our knowledge, there are less than five horizontal municipal water
supply wells in Colorado. We have already conducted basic research into different types of
horizontal wells and installation approaches. In the MWE memo to Dave Lindsey (Colorado Civil
Group, Inc.) dated December 9, 2018, we concluded that a horizontal well installed by trenching will
likely "provide the greatest reliability and operational flexibility" for the Town. In the same memo,
we discussed how we developed and calibrated a groundwater model that we believe accurately
predicts H-well production with and without MAR. Today, we still conclude that a horizontal well
installed by open trenching (rather than directional drilling) will provide the greatest reliable yield for
the town, but due to the aforementioned uniqueness of such wells, and in particular the unique
situation of installing that well by open trenching, there are numerous design and logistical
construction considerations to be evaluated.
Numerous details still to be evaluated, in part by modeling, include; (i) well construction materials
such as wrapped -screen stainless steel vs, perforated PVC pipe, both of which have a range of open
areas; (ii) whether using two smaller diameter perforated well pipes is better than using one larger
well pipe; (iii) trench location relative to Pelican Shores; and (iv) ongoing consideration of MAR
scheduling and recharge rates along with monthly extraction scenarios.
Geoteehnical drilling and testing also needs to be done early in the design phase. Geotechnical
drilling (sites not yet determined) and laboratory tests are important to developing a safe excavation
program and evaluate foundation design options. Figure 1 shows the four proposed additional
monitoring wells located around the site perimeter plus another one near Pelican Shores' homes to
monitor sub -basement groundwater levels.
1VIcGrane Water Engineering, LI.0
1669 Apple Valley Rd. •Lyons, CO 80540 •Phone: (303) 917-1247
&Mail: Bennis �� mein auewatcr,1 0com
AWE Horizontal Well, Pump, Pump House and Pipeline Proposal Page 5 of 11
December 16, 2019
Therefore, under Task 2 of this project, we propose the following pre -design tasks:
• Task 2.1 —Researching and evaluating: horizontal well design options such as screen
materials and open area, plus construction/trenching techniques and wet well options
(precast and cast in place).
• Task 2.2 - Computer modeling various: screen materials and designs; horizontal well
locations; recharge trench locations, depths and widths; delivery periods and rates; and
potential impacts to Pelican Shores. We will prepare a memo* to the Town describing
our "preferred design" recommendations.
• Task 2.3 —Researching and computer modeling of dewatering options (prior to and
during construction) and documenting our conclusion summary in an internal
memorandum*; and
• Task 2.4 — Geotechnical drilling, sampling and testing, and monitoring well installation at
approximately 3 to 5 locations. In addition, a preconstruction site survey is necessary to
prepare a site plan and identify existing utilities and easements.
Cont��actor Cost Estimates: $50,000 for geotechnical engineering, drilling, laboratory analysis,
monitoring well installation and a site survey which will be subcontracted through MWE.
We will design and prepare a single contractor bid package for six critical project components.
�iaal Hoa�azzontal Tell azad 7'es I�esi,�
The design of both horizontal well segments (current segment and potential future expansion) and
wet -well vault must comply with the Colorado Water Well Construction rules and meet the design
review requirements of the Colorado Department of Health and Environment (CDPHE). We will
prepare preliminary designs prior to finalizing the bid documents and meet with regulators to get
them involved with this iterative process.
We will conduct extensive tests with a temporary pump after the H-well is installed. For budgeting
purposes, we anticipate testing will include: 1) conducting a 5-day pumping test at 150 to 300 gpm
to determine the minimum sustainable pumping rate; and 2) conducting a 5-day recharge pumping
test at pumping rates up to 1,200 gpm to determine maximum sustainable recharge and pumping
rates. This plan may be revised based on additional computer modeling or based on the partially
dewatered condition of the aquifer at the end of well construction. MGE will interpret the pumping
test with the computer model. The test results will be used to finalize the permanent pump design.
Dewate'
Although each bidder will be asked to provide a dewatering plan with their bid, we plan to also use
our site groundwater model to evaluate the feasibility of their proposals. Our dewatering modeling
M
cGrane Water Engineering, LLC
1669 Apple Valley Rd. •Lyons, CO 80540 •Phone: (303) 917-1247
&Mail: dcnuis«mc,nauew�itcr.com Web: Up://tvwt�.mcgranewatercnginccring.com
MWE Horizontal Well, Pump, Pump House and Pipeline Proposal
December 16, 2019
Page 6 of 11
objectives are to: (i) identify reasonable dewatering approaches (vertical wells, open sump
excavations, or both); (ii) reduce construction time; and (iii) minimize impacts to the Pelican Shores
Lake. MGE will conduct the modeling, document our results in a task memorandum* and use the
results to evaluate the dewatering proposals provided by contractors.
Acuity will evaluate the structural and hydraulic benefits of both precast or a cast -in -place design
options and decide which is(are) acceptable. The design must also meet CDWR and CDPHE
construction requirements discussed above. For budgeting purposes, we have assumed the "highest
cost" option that involves installing a 10 foot square cast -in -place vault as the wet -well that could
cost approximately $250,000.
Piunp House
The pump house will be a basic wood -framed design on a foundational slab with footings. The
building will be insulated and heated. The piping will likely be sized for two pumps, each capable of
providing 200 to 550 gpm (maximum 20 horsepower).
Elechic Service
We anticipate using 480v three-phase power. We will coordinate power to the site by contacting
United Power and providing load demands for the pump and pump house. The cost will vary
depending on whether power comes from south of the site (on CR 26), or from an existing
transformer located across Colorado Blvd near the proposed well house. It will likely take 3 to 4
months for United Power to review our design and bring power to the site.
�'umpmg System and Controls
Our contractor cost estimate below is based on assuming two 20-horsepower vertical turbine pumps
one primary and one back-up) installed in the well house above the wet -well vault with Variable
Speed Drives (VFD). MWE and Acuity will work together to size and design the system prior to
construction, but may revise the final pump design after testing is complete.
At the request of CCG, we are not including System Control and Data Acquisition (SCADA)
components in our scope of work. We request that the Town provide us necessary considerations
for SCADA to be installed at a later date, which may include oversized control panels or specialized
water level transducers or electronic flow meters.
Design Tasks include:
• Task 3.1 —Prepare final H-well design plans and specifications that considers Colorado
Department of Water Resources (CDWR) and CDPHE design and permit requirements.
• Task 3.2 — Comply with CDWR rules and CDPHE design and permit requirements.
• Task 3.3 — Evaluate wet -well vault structural and hydraulic considerations and prepare
design plans and specifications,$
iVLcGrane Water Engineering, LLC
1669 Apple Valley Rd. •Lyons, CO 80540 •Phone: (303) 917-1247
&A4ai1: dcnnis@mc�rane��ater.com 1Vcb; ttp://���aa�,megranc��alercn�;inecrin�;.com
MWE Horizontal Well, Pump, Pump House and Pipeline Proposal
December 16, 2019
• Task 3.4 — Prepare pump house design plans and specifications,
• Task 3.5 — Obtain adequate power for the site through United Power;
• Task 3.6 — Prepare contractor bid package; and
• Task 3.7 — Project management activities.
Page 7 of 11
Project management actives include managing engineers and contractors, attending bimonthly
status meetings with CCG and the Town and various administrative tasks.
'Task 4, ®Construction and Testing
Construction related tasks and budget assumptions in parentheses include:
• Task 4.1 -Evaluate bids; interview contractors and assist with contracting;
• Task 4.2 - Preconstruction dewatering administration (if required up to 10 man -days);
• Task 4.3 - H-well and wet -well vault construction administration (up to 60 man -days on
site);
• Task 4.4 - Recovery and recharge pump test administration and interpretation (up to 12
man -days on site);
• Task 4.5 —Final pump design;
• Task 4.6 — Pipeline construction administration;
• Task 4.7 — Pump house construction administration; and
• Task 4.8— Project management activities
Contfactor Cost Estr.mates and Assumptions: Construction dewatering = $155,000; H-well =
$320,000 plus potentially $250,000 for a cast -in -place wet -well (vault); Pumps = $100,000; Pump
house = $135,000; pipeline $150,000; and power to pump station = $150,000 for United Power. We
assume that no 404 permit is required to recharge dewatering discharge water along on the west side
A the Varra property.
IN "MIUM MIS
Task 5 includes:
• Task 5.1 —Pump installation and start-up administration; and
• Task 5.2 —Prepare completion and testing report and submittal manual.
Table 1 summarizes our opinion of probable cost for the project.
IvicGrane Water Engineering, I�LC
1669 Apple Valley Rd. •Lyons, CO 80540 •Phone: (303) 917-1247
&Mail: dcnnis �� inc�ru�cwatcr.com �Veb: ttp://www.me�rancwatcrengiuecring.com
MWE Horizontal Well, Pump, Pump House and Pipeline Proposal
December 16, 2019
Table 1- Opinion of Probable Cost for H-well, Pump, Pump House and Pipeline
Page 80111
Opinion of Probable Cost - Well, Pump Station & Pipeline Design and Installation (12/16/2019)
Task
Task Description
Weeks
Team 1 Engineering
()
Contractor
Task Total
$
Cost
Estimate $
T e
Type
1.0-.Plannin
1.1
lPreliminary Design (complete)
$20,000
-
$20,000
1.2
Contractin
$3 000
Task 1 Subtotal
Mna
$239000
-
$23,000
2.0 - Research, Modeling and Geotech
2.1
Research Desi O tions
$23,000
-
$235000
2.2
Computer Modeling Scenarios
8
$2%000
-
$29,000
2.3
Evaluate Dewatering Options
1
$125000
-
$12,000
2.4
Geotech Drilling and Surveying
2
$67,000
$17,000
Task 2 Subtotal
12
$131,000 1
$0
$81,000
3.0 - Design
3.1
Final Horizontal Well Design
2
$9,000
-
$95000
3.2
CDPHE System Design Review
4
$13,000
-
$13,000
3.3
Design Pump Vault
4
$59,000
-
$59,000
3A
Design Pump Station and Pipeline
4
$295000
-
$295000
3.5
Electrical Eng and United Power
12 46
$165000
$150,000
United
Power
$1663000
3.6
Prepare Contractor Bid Package
4
$345000
-
$343000
3.7
jProject Management Activities
16
$215000
-
$213000
Task 3 Subtotal
16
$181,000
$150,000
$331,000
4.0 "Construction and Testing
4.1
Contracting and Mobilization
5
$3,000
-
$3,000
4.2
Construction Dewatering
4
$20,000
$155,000
Excavator
$175,000
4.3
H-well and Vault Cons. Admin.
10
$98,000
$565,000
Excavator
$663,000
4.4
Recovery and Recharge Tests
4
$29,000
-
$293000
4.5
Final Pump Design
2
$13,000
-
$133000
4.6
Pipeline Construction
6
$%000
$150,000
Pipeline
$159,000
4.7
Pump House Construction
6
$5,000
$135,000
Building
$140,000
4.8
Project Management Activities
na
$1000
$10,000
Task 4 Subtotal
20
$187 000
$1 005 000
$1 192 000
5.0 - Pump Installation and Start-up Report
5.1
IPump Installation and Startup
2-3
$5 000
$100,000
Pump
$105,000
5.2
ITesting Report and O&M Manual
2-3
$20,000
-
$20,000
Task 5 Subtotal
4-6
$25,000
$1005000
$1255000
Total
$547,000
$1,255,000
$19752,000
Contingency
Percent
40%
Total $
$5025000
$502,000
Grand Total
1
9
$2,2541000
Notes: 1) Design Team includes: McGrane Water Engineering, LLC (MWE), Acuity, Inc,, Miller Groundwater Engineering,
LLC, and Casare Inc, * See Gantt chart for schedule of each subtask.
McGrane Water Engineering, LLC
1669 Apple Valley Rd. •Lyons, CO 80540 •Phone: (303) 917-1247
E-Mail: dcnnis@mcgranctvatcr,com \��eb: ltp://��-w�r,mcgraner�-atercnt;iueeriug.com
AWE Horizontal Well, Pump, Pump House and Pipeline Proposal
December 16, 2019
Page 9 of 11
We estimate that the engineering related tasks described above can be completed for $547,000. The
total cost for engineering and construction is $1,752,000. Due to the high uncertainty in construction
costs, we added a 40% contingency totaling $502,000. The greatest component of uncertainty is the
H-well installation which could take 60 to 90 days depending on the dewatering and trenching methods
and effectiveness. Therefore, we recommend that the Town budget $2,254,000 for the project. This
is $154,000 more than our preliminary cost estimate provided last year, but the earlier estimate did not
include the water pipeline to the water treatment plant (MWE, 12-94 8). Our current proposal also
does not include: drainage improvements, permanent access roads or security fencing, existing trench
restoration or SCADA equipment for remote operation or data collection.
Payments for our services, like other professional services, are based on the actual time spent on your
behalf and at hourly rates offered for this specific project scope ($168/hr for Dennis McGrane
(MWE), $193/hr for Kevin O'Connell (Acuity) and $145/hr for Calvin Miller (MGE). Billing occurs
on a monthly basis and payment is expected within 30 days.
We request the Town:
• Subcontract separately with contractors shown on Table l .
• Arrange permission with the Pelican Shores HOA to drill one additional permanent
monitoring well on their property (Figure 1) which we will equip with a water level
sensor to monitor water levels during testing. At a later date, the Town may decide to
install a continuous data logger with SCADA to provide continuous, real-time monitoring
of water levels at that location, or similar, near the Pelican Shores basements.
• Request permission from the Pelican Shores HOA to discharge some of our construction
dewatering water to their lake due to the fact that that our construction dewatering
pumping will be much more intense than future water -supply operations. We would like
to pursue two dewatering discharge options: (1) route water to the river directly north
along CR 13 right of way or possibly along the existing tail water path to the east (used
during the Fall 2018 recharge test), and (2) to Pelican Shore Lake through a pipe routed
under CR13 via an existing irrigation culvert. Having both options may be necessary to
mitigate real and perceived impacts with the HOA. We believe the State would likely
grant us dewatering discharge permits for both. To accomplish this, we ask the Town to
request permission from the HOA to discharge our water to their lake.
• Acquire the necessary water rights for the project and arrange for surface water deliveries
in September and October, 2020 for H-well and MAR testing.
• Obtain permission to install temporary discharge piping to allow dewatering discharge to
recharge between the Varra property and Colorado Blvd,
McGrane Water Engineering, LLC
1669 Apple Valley Rd. •Lyons, CO 80540 •Phone: (303) 917-1247
l;-Mail: Bennis«mcgrane��aLer.coin Wcb; ttp://������:mcgranc«-atercn�incering.com
MWE Horizontal Well, Pump, Pump House and Pipeline Proposal
December 16, 2019
Page 10 of 11
T ime Required
We envision the project can be completed in 13 months by March 2021, Appendix A includes a
Gantt chart that shows how some tasks overlap. Delays caused by circumstances beyond the control
of the engineer could extend the time of completion.
Risk
It should be understood that the well type and installation method we have selected for this well is
arguably unique for high -capacity water wells and contains several site -specific considerations. If a
more common type and more routine installatimi method had been the highest priority, then we
might have given more consideration to selecting multiple vertical wells, or large diameter vertical
wells, or alternative H-well installation methods. However, at the Town's direction, the highest
priority for this well has been clear: provide the best reliable yield possible given the hydrogeologic
limitations of the site. That directive includes providing the desired yield at times with lower aquifer
water levels, such as what might occur many months between potentially seasonal recharge
operations. In response, we did consider several other options, but concluded that a horizontal well,
installed via open trenching, is the preferred approach for the site conditions.
There is also risk when constructing any type of well, since there is uncertainty and variability in
aquifer properties away from where test drilling occurred, plus uncertainties associated with
groundwater modeling projections. Actual performance maybe different from expected and
projected performance, Finally, our consulting services have been limited to assessing site
hydrogeologic conditions and projecting sustainable yield of a wellfield at the site. We have not
been closely involved with all associated decisions such as characterizing the water quality or
evaluating the cost -benefits of other water supply options.
Contracting
We envision the Town will include this proposal as an attachment in their standard professional services
contract and MWE will subcontract work to other consultants as needed.
We look forward to working the Town of Firestone and CCG on this project.
Sincerely,
MCGRANE WATER ENGINEERING, LLC.
Dennis McGrane, P.E., C.P.G.
Principal Engineer and Hydrogeologist
McGxane Water Engineering, LLC
1669 Apple Valley Rd. •Lyons, CO 80540 •Phone: (303) 917-1247
L�. Mail: Bennis �� mc�naucwater.com \��eb: up.//�t�at��.mcgranew<ilcrcn�ineering.com
Task
Task Description
2019
Apr -
December
2020
Jan Feb Mar Apr May June July Aug Sep Oct Nov Dec
2021
Jan
1) Planning
a
Preliminary Design and SOW
2) Research,
Modeling and
a
Modeling Design and Dewatering Options
Geotech Work
b
ISurveying, Geotech Drilling, and Permitting
3) Design
a
Design H-Well, Vault, Pump, and Building
b
Prepare Plans and Specs and Bid
4) Construction
and Testing
a
Contracting and Mobilization
b
Dewatering
c
Trench Construction Observation
d
Recovery and Recharge Test Observation
e
Pipeline, and Building Installation
5) Pump
Installation and
Startup Test
a
Pump Installation and Startup
b
Prepare Completion and Testing Report