HomeMy WebLinkAboutCARMA 14-35 - Well Abandonment Report - Kerr McGee - 4/15/2024Casing History
Subsequent Report of Abandonment
Details:
If yes, explain details below
If yes, explain details below
Yes NoWellbore has Uncemented Casing leaks:
NoYesFish in Hole:
Estimated Depth:NoYesCasing to be pulled:
Other
Mechanical ProblemsProduction Sub-economicDryReason for Abandonment:
-104.97600640.177558 Longitude:
GPS Data:
Only Complete the Following Background Information for Intent to Abandon
2.7 09/10/2008GPS Quality Value:Date of Measurement:
Latitude:
Type of GPS Quality Value:PDOP
90750Field Number:Field Name:WATTENBERG
Federal, Indian or State Lease Number:
Meridian:668W Range:Township:3N 35Section:QtrQtr:
14-35 Well Number:
SWSW
County:WELD
Location:
CARMAWell Name:
05-123-24914-00API Number
This form is to be submitted as an Intent to Abandon whenever an abandonment is planned on a borehole. After the
abandonment is complete, this form shall again be submitted as a Subsequent Report of the actual work completed. The
approved intent shall be valid for six months after the approval date, after that period, a new intent will be required.
Attachments required with the Intent to Abandon are wellbore diagrams of the current configuration and the proposed
configuration with plugs set.
A Subsequent Report of Abandonment shall indicate the actual work completed. Attachments required with a Subsequent
Report are a wellbore diagram showing plugs that were set and casing remaining in the hole, the job summaries from all
plugging contractors used, including wireline and cementing (third party verification) and any logs that may have been run
during abandonment.
State of Colorado
Energy & Carbon Management Commission
1120 Lincoln Street, Suite 801, Denver, Colorado 80203 Phone: (303) 894-2100 Fax: (303) 894
-2109
WELL ABANDONMENT REPORT
FORM
6
Rev
11/20
Notice of Intent to Abandon
lorena_ruiz@oxy.comEmail:
Fax:
(970) 336-3535Phone:
Zip:80217-
3779
COState:DENVER
P O BOX 173779
Contact Name:
City:
Lorena Ruiz
Address:
KERR MCGEE OIL & GAS ONSHORE LPName of Operator:
47120ECMC Operator Number:
craig.carlile@state.co.usEmail:
Tel:(970) 629-8279Name:Carlile, Craig For "Intent" 24 hour notice required,
ECMC contact:
04/01/2024
Date Received:
Document Number:
DE ET OE ES
403737755
Formation Perf. Top Perf. Btm Abandoned Date Method of Isolation Plug Depth
CODELL 7448 7468
NIOBRARA 7246 7326
Total: 2 zone(s)
Current and Previously Abandoned Zones
Type of Well Abandonment Report:
Page 1 of 4Date Run: 4/8/2024 Doc [#403737755] Well Name: CARMA 14-35
Technical Detail/Comments:
Additional Plugging Information:
Perforate and squeeze at 1020ft. with 95 sacks. Leave at least 100 ft. in casing 990 CICR Depth (Cast Iron Cement Retainer)
Eagle Buffer:
This planned location is located within a bald eagle buffer. Operations will need to be completed outside the timing windows of 12/1 –
7/31 (eagle nest) and/or 11/15 – 3/15 (winter night roost). The eagle nest buffer window can be shortened if the nest has been
confirmed fledge for the year by CPW. If work, is planned during either window, HSE will consult with CPW prior to operations
beginning. CPW CONSULTATION HAS BEEN COMPLETED.
NoYesFlowline/Pipeline has been abandoned per Rule 1105
Type of Cement and Additives Used:
*Cementing Contractor: *Wireline Contractor:
Cut and Cap Date:
inch casingft. of
Additional Plugging Information for Subsequent Report Only
Casing Recovered:
Plug Tagged: Plug Type:
Plug Tagged:CASINGPlug Type:
Plug Tagged:CASINGPlug Type:
Plug Tagged:CASINGPlug Type:
Plug Tagged:CASING
Plug Tagged:
(Cast Iron Cement Retainer Depth)
CICR Depth
CICR Depth
2160
4118
CICR Depth7216
sacks cmt on top.withCIBP #5: Depth
sacks cmt on top.withsacks cmt on top. CIBP #4: DepthwithCIBP #3: Depth
Set sacks in mouse holeSetsacks in rat hole
NoYesAbove Ground Dry-Hole Marker:Cut four feet below ground level, weld on plate
44Set sacks at surface
ft.170ft. to655sacks half in. half out surface casing fromSet65
sacks. Leave at least 100 ft. in casing210ft. with2800Perforate and squeeze at
sacks. Leave at least 100 ft. in casing95ft. with4148Perforate and squeeze at
sacks. Leave at least 100 ft. in casing95ft. withPerforate and squeeze at 7246
ft. ft. tosks cmt fromSet
ft. 930ft. to990sks cmt fromSet5
ft. 2000ft. to2160sks cmt fromSet15
ft. 4155ft. to4118sks cmt fromSet5
ft. 7155ft. to7216sks cmt from5Set
sacks cmt on top.withsacks cmt on top. CIBP #2: Depth44with150CIBP #1: Depth
Plug Type:
NOTE: Two(2) sacks cement
required on all CIBPs.
Plugging Procedure for Intent and Subsequent Report
Casing Type Size of
Hole
Size of
Casing
Grade Wt/Ft Csg/Liner
Top
Setting
Depth
Sacks Cmt Cmt Btm Cmt Top Status
SURF 12+1/4 8+5/8 J-55 24 0 555 640 555 0 VISU
1ST 7+7/8 4+1/2 I-80 11.6 0 7606 635 7606 3442 CBL
S.C. 1.1 7+7/8 4+1/2 I-80 11.7 0 7606 350 1475 230 CBL
JENKINS, STEVE
Based on the information provided herein, this Well Abandonment Report (Form 6) complies with COGCC Rules and applicable
orders and is hereby approved.
ECMC Approved:Date:4/8/2024
I hereby certify all statements made in this form are, to the best of my knowledge, true, correct, and complete.
Signed:Print Name:Lorena Ruiz
Title:Regulatory Tech Date:4/1/2024 Email:lorena_ruiz@oxy.com
Surface Plug Setting Date:
Number of Days from Setting Surface Plug
to Capping or Sealing the Well:
Page 2 of 4Date Run: 4/8/2024 Doc [#403737755] Well Name: CARMA 14-35
10/7/2024Expiration Date:
COA Type Description
Due to proximity to a mapped wetland, surface water and expected shallow
groundwater, operator will use secondary containment for all tanks and other liquid
containers. Operator will implement stormwater BMPs and erosion control measures as
needed to prevent sediment and stormwater runoff from entering the wetland and
surface water.
Due to close proximity to Residential Building Units (RBUs), prior to commencing
operations, at a minimum, the operator will provide an informational sheet to the
owners/occupants of the RBUs nearby and adjacent to the parcel with the well. The
sheet will include the operator's contact information and the nature, timing, and
expected duration of the P&A operations. Operator will implement measures to capture,
combust, or control emissions to protect health and safety, and to ensure that vapors,
odors and noise from plugging operations do not constitute a nuisance or hazard to
public health, welfare and the environment.
Operator committed to the following Best Management Practices under the Technical
Detail/ Comments section on the Submit Tab and in attached communication with CPW:
This planned location is located within a bald eagle buffer. Operations will need to be
completed outside the timing windows of 12/1 – 7/31 (eagle nest) and/or 11/15 – 3/15
(winter night roost). The eagle nest buffer window can be shortened if the nest has been
confirmed fledge for the year by CPW. If work, is planned during either window, HSE
will consult with CPW prior to operations beginning.
Bald Eagle Winter Night Roost: 11/15 – 3/15 operations only between 10am – 2pm. It is
our intent to finish any
work in BEWNR prior to 11/15.
FLOWLINE AND SITE CLOSURE
1)Consistent with Rule 911.a, a Form 27 must be approved prior to cut and cap,
conducting flowline abandonment, or removing production equipment. Allow 30 days for
Director review of the Form 27; include the Form 27 document number on the Form 44
for offsite flowline abandonment (if applicable) and on the Form 6 Subsequent.
2)Properly abandon flowlines per Rule 1105. If flowlines will be abandoned in place,
include with the Form 27: pressure test results conducted in the prior 12 months as well
as identification of any document numbers for a ECMC Spill/Release Report, Form 19,
associated with the abandoned line.
1) Provide 2 business day notice of plugging MIRU via electronic Form 42, and provide
48 hours Notice of Plugging Operations, prior to mobilizing for plugging operations via
electronic Form 42. These are 2 separate notifications, required by Rules 405.e and
405.I.
2) Prior to placing the 655’ plug: verify that all fluid migration (liquid and gas) has been
eliminated. If evidence of fluid migration or pressure remains, contact ECMC Engineer
for an update to plugging orders.
3) After isolation has been verified, pump surface casing shoe plug. If cement is not
circulated to surface, shut-in, WOC 4 hours then tag plug – must be at 505’ or shallower
and provide 10 sx plug at the surface.
4) Leave at least 100’ of cement in the wellbore for each plug without mechanical
isolation.
5) After cut and prior to cap, verify isolation by either a 15 minute bubble test or 15
minute optical gas imaging recording. If there is indication of flow contact ECMC
Engineering. Provide a statement on the 6SRA which method was used and what was
observed. Retain records of final isolation test for 5 years.
6) With the Form 6 SRA operator must provide written documentation which positively
affirms each COA listed above has been addressed.
CONDITIONS OF APPROVAL, IF ANY:
Page 3 of 4Date Run: 4/8/2024 Doc [#403737755] Well Name: CARMA 14-35
Prior to starting plugging operations a Bradenhead test shall be performed if there has
not been a reported Bradenhead test within the 60 days immediately preceding the start
of plugging operations.
1) If, before opening the Bradenhead valve, the beginning pressure is greater than 25
psi, sampling is required.
2) If pressure remains at the conclusion of the test, or if any liquids were present during
the test, sampling is required.
The Form 17 shall be submitted within 10 days of the test. Sampling shall comply with
Operator Guidance - Bradenhead Testing and Reporting Instructions. If samples are
collected, copies of all final laboratory analytical results shall be provided to the ECMC
within three (3) months of collecting the samples.
6 COAs
Attachment List
Att Doc Num Name
403737755 WELL ABANDONMENT REPORT (INTENT)
403737839 PROPOSED PLUGGING PROCEDURE
403737841 OTHER
403737851 WELLBORE DIAGRAM
403746662 FORM 6 INTENT SUBMITTED
Total Attach: 5 Files
User Group Comment Comment Date
OGLA Location Assessment Specialist review complete.04/08/2024
Permit selected PDOP from dropdown box
Verified as drilled lat/long
Verified completed intervals - 12324914(2), 12324914
Verified production reporting
pass
04/02/2024
Engineer If any changes during the plugging are needed, please email Steve Jenkins at
Steve.Jenkins@state.co.us. Since Curtis has moved over to the UIC group, I am taking
over the review and follow up on his Intents.
Thanks,
Steve
04/01/2024
Engineer 1) Deepest Water Well within 1 mile = 500’.
2) Fox Hills Bottom- 77’, per SB5.
04/01/2024
Total: 4 comment(s)
General Comments
Page 4 of 4Date Run: 4/8/2024 Doc [#403737755] Well Name: CARMA 14-35