HomeMy WebLinkAboutKUGEL V 18-4 & KUGEL 12-18 - Start of Plugging Operations - Kerr McGee - 4/24/2024From: Wells, Matt <Matthew_Wells@oxy.com>
Sent: Wednesday, April 24, 2024 7:27 AM
Subject: Plug and Abandon operations on the KUGEL V 18-4 and the KUGEL 12-18 wells
Good morning Firestone team,
I want to inform you that in late June or early July of this year, KMOG plans to Plug and Abandon (P&A) the above
mentioned wells. This is that same area we were talking about a few weeks ago (after Crestone crews damaged the
trail and field). I have already been in contact with our P&A Operations teams about this area and instructed them to
take extra care when they are in this area. Any damage caused by the workover rig to the trail or field will be
immediately repaired.
A few days before we begin operations you (and the fire district) will receive the standard (and State ECMC required)
Rule 903.a potential flare notice email. You will also see in a few weeks, the required Rule 1105.d Flowline removal
notice email for these two wells.
Please let me know if you have any questions.
The red dots are the KMOG wells to be P&A’d. The yellow dots are Crestone wells.
Matt Wells
REGULATORY ADVISOR
Office: 720.929.3403 | Mobile: 970.310.3110 |
Zero In™ at oxy.com