HomeMy WebLinkAbout21-18 Performance of Schedule A 2021 Work Orders IPT Inc Injection Well 01-27-2021RESOLUTION N0.21-18
A RESOLUTION OF THE BOARD OF TRUSTEES OF THE TOWN OF FIRESTONE,
COLORADO, AUTHORIZING PERFORMANCE OF THE SCHEDULE A FISCAL
YEAR 2021 WORK ORDERS AS SET FORTH IN THE PROFESSIONAL SERVICES
AGREEMENT BETWEEN THE TOWN OF FIRESTONE AND NEW IPT INC.
REGARDING THE ST. VRAIN WATER TREATMENT PLANT INJECTION WELL
WHEREAS, by adoption of Resolution No. 20-31 the Town of Firestone ("Town")
selected and approved a Professional Services Agreement ("Agreement") with New IPT Inc. to
perform engineering services regarding the development, oversight, and coordination of a drilling
plan and facility design services for the St. Vrain Water Treatment Plant ("Project"); and
WHEREAS, Schedule A of the Agreement sets forth Project Work Orders which requires
that the Town by resolution authorize New IPT Inc. to commence performance of the Project's
Fiscal year 2021 Work Orders; and
WHEREAS, the parties now desire to commence performance of the Project's fiscal year
2021 Work Orders,
NOW, THEREFORE, BE IT RESOLVED BY THE BOARD OF TRUSTEES OF THE
TOWN OF FIRESTONE, COLORADO:
As set forth in the Professional Services Agreement between the Town of Firestone and
New IPT, Inc., the Town of Firestone authorizes New IPT Inc. to commence performance of the
Project's fiscal year 2021 Work Orders.
INTRODUCED, READ AND ADOPTED this 27th day of January, 2021.
ATTEST:
APPROVED AS TO
°'• rQ
�o STco0 0
*6000
Y,Q-
Attorney
OF FI STONE, COLORADO
SCHEDULE A
(Attached to and made part of the Agreement between Town of Firestone and New IPT, Inc.
dated March 11, 2020)
IPT Project Name: Town of Firestone SWD #1, Task: Drilling Engineering (Work Order
2020A1) $175,000 in the 2020 budget - Completed in 2020
Worlc Order 2020-1 is for the development of a detailed drilling plan, management of drilling
logistics, and subsequent analysis as follows:
Subpart O1: Development of a well Basis of Design (BOD) including offset well and bit analysis,
expected days -vs -depth curve, detailed casing and cementing design, recommended vendor
determination, expected performance analysis, determination of quality objectives, and
determination of contractor key performance indicators (KPIs). This subpart also includes an
authority -for -expenditure (AFE) and client meeting.
Subpart 02: Drilling Engineering including issuance of request for quotes (RFQs), evaluation, and
award. Additionally, this subpart includes review of any special issues arising during drilling.
Subpart 03: Drilling Engineering Detailed Drilling Plan with operational procedures including
detailed drilling fluids, cementing, bit program, emergency response plan, and wellhead and
operational checklists. This subpart includes all documentation required for onsite operations.
Subpart 04: Drill the Well on Paper (DWOP) meeting including all relevant contractors and the
client, held approximately two weeks prior to moving in the drilling rig. Subpart 05: Onsite
Prespud Meeting, held on location just prior to spud.
Subpart 05: Drilling Engineering End of Well Reports which includes consolidation of all reports
and logs subsequent to drilling, an as -built wellbore diagram, performance assessment of
objectives, and KPIs. This subpart includes a client meeting to review.
The budget for 2020-01 is $175,000 and is estimated to be incurred over the period from September
2020 through December 2020. The project will be billed twice a month beginning in September
through December in $21,875 installments.
IPT Project Name: Town of Firestone SWD #1, Task: Drilling and Completions Operations
Management (Work Order 2020-02) $4,000 in the 2020 budget - $0.00 completed in 2020,
remaining $4,000.00 to be completed in 2021
Work Order
Order 2020-02 is for drilling and completions operations management including daily field
support, morning calls, and operations engineering support.
The budget for 2020-02 is $4,000 to be billed as a lump sum when the well is spudded. The spud
date is anticipated to be in November 2020.
IPT Project Name: Town of Firestone SWD #1, Task: Completion Engineering (Work Order
2020-03) $15,000 in the 2020 budget- $0.00 completed in 2020, remaining $15,000.00 to be
completed in 2021
Work Order number 2020-03 is for completions engineering work including development of
completion programs, issuance of RFQs, evaluation and award, end of well report and as -built
wellbore diagram.
The budget for 2020-03 is $15,000 to be billed as a lump sum prior to the start of well completion
operations. This project is anticipated to be completed by December 31, 2020.
IPT Project Name: Town of Firestone SWD #1, Task: Drilling Wellsite Supervision (Work
Order 2020-04) $78,000 in the 2020 budget - $0.00 completed in 2020, remaining $78,000.00
to be completed in 2021
Work Order 2020-04 is for drilling Wellsite supervision with two on -site personnel to oversee,
coordinate, and direct activities during the drilling of the well.
The budget for 2020-04 is $78,000 to be billed at $3,900 per day. This project is anticipated to
commence in November 2020 and be completed by the end of December 2020 and will be
invoiced every two weeks.
IPT Project Name: Town of Firestone SWD #1, Task: Injection Facility Design (Work Order
2020-OS) $90,000 in the 2020 budget - $41,173.25 completed in 2020, remaining $48,826.75 to
be completed in 2021
Work Order 2020-05 is for the injection pump facility design including design, RFQs, bid analysis,
award, and final construction documents. This also includes costs of obtaining grading, excavating
and stormwater plans necessary to obtain the relevant permits.
The budget for 2020-O5 is $90,000 to be billed at $225 per hour. This project will commence in
March 2020 and go through December 2020 and will be invoiced every two weeks.
The additional worlr orders below are fos• fiscal year 2021 and fvill require separate aUproval
bV the Towfz of Fir•estoyie Board of Trristees.
IPT Project Name: Town of Firestone SWD 41, Task: Facilities Commissioning (Work
Order 2021-01) $5,000 in the 2021 budget
Work Order 2021-01 is for engineering and field supervision necessary to monitor installation
and commissioning of the injection pump facility.
The budget for 2021-01 is $5,000 to be billed at $225 per hour. This project will be delivered
during 2021 and invoiced every two weeks.
IPT Project Name: Town of Firestone SWD #1, Task: Completion Supervision (Work
Order 2021A2) $40,000 in the 2021 budget
Work Order 2021-02 is for completions supervision with on -site personnel to oversee, coordinate
and direct activities during the well completion.
The budget for 2021-02 is $40,000 to be billed at $2,000 per day. This project is anticipated to
commence in January 2021 and complete in May 2021 and will be invoiced every two weeks.