HomeMy WebLinkAboutADAM FARM 8-4 - Well Abandonment Report - Kerr McGee - 4/13/2021Casing History
Subsequent Report of Abandonment
Details:
If yes, explain details below
If yes, explain details below
Yes NoWellbore has Uncemented Casing leaks:
NoYesFish in Hole:
Estimated Depth:NoYesCasing to be pulled:
Other
Mechanical ProblemsProduction Sub-economicDryReason for Abandonment:
-105.00404140.171241 Longitude:
GPS Data:
Only Complete the Following Background Information for Intent to Abandon
Renee Doiron2.711/09/2009 GPS Instrument Operator's Name:PDOP Reading:Date of Measurement:
Latitude:
90750Field Number:Field Name:WATTENBERG
Federal, Indian or State Lease Number:
Meridian:668W Range:Township:2N 4 Section:QtrQtr:
8-4 Well Number:
SWNE
County:WELD
Location:
ADAM FARMWell Name:
05-123-30568-00API Number
This form is to be submitted as an Intent to Abandon whenever an abandonment is planned on a borehole. After the
abandonment is complete, this form shall again be submitted as a Subsequent Report of the actual work completed. The
approved intent shall be valid for six months after the approval date, after that period, a new intent will be required.
Attachments required with the Intent to Abandon are wellbore diagrams of the current configuration and the proposed
configuration with plugs set.
A Subsequent Report of Abandonment shall indicate the actual work completed. Attachments required with a Subsequent
Report are a wellbore diagram showing plugs that were set and casing remaining in the hole, the job summaries from all
plugging contractors used, including wireline and cementing (third party verification) and any logs that may have been run
during abandonment.
State of Colorado
Oil and Gas Conservation Commission
1120 Lincoln Street, Suite 801, Denver, Colorado 80203 Phone: (303) 894-2100 Fax: (303) 894
-2109
WELL ABANDONMENT REPORT
FORM
6
Rev
05/18
Notice of Intent to Abandon
jennifer_thomas@oxy.comEmail:
Fax:
(720) 929-6808Phone:
Zip:80217-
3779
COState:DENVER
P O BOX 173779
Contact Name:
City:
Jennifer Thomas
Address:
KERR MCGEE OIL & GAS ONSHORE LPName of Operator:
47120OGCC Operator Number:
robbie.revas@state.co.usEmail:
Tel:(720) 661-7242Name:Revas, Robbie For "Intent" 24 hour notice required,
COGCC contact:
02/13/2020
Date Received:
Document Number:
DE ET OE ES
402312324
Formation Perf. Top Perf. Btm Abandoned Date Method of Isolation Plug Depth
CODELL 7482 7500
J SAND 7926 7958
NIOBRARA 7220 7362
Total: 3 zone(s)
Current and Previously Abandoned Zones
Page 1 of 4Date Run: 2/18/2020 Doc [#402312324] Well Name: ADAM FARM 8-4
*ATTACH JOB SUMMARY
Technical Detail/Comments:
8/17/2020Expiration Date:
NoYesFlowline/Pipeline has been abandoned per Rule 1105
Type of Cement and Additives Used:
*Cementing Contractor: *Wireline Contractor:
Cut and Cap Date:inch casingft.
of
Additional Plugging Information for Subsequent Report Only
Casing Recovered:
Plug Tagged: Plug Type:
Plug Tagged: Plug Type:
Plug Tagged: Plug Type:
Plug Tagged: Plug Type:
Plug Tagged:
Plug Tagged:
(Cast Iron Cement Retainer Depth)
CICR Depth
CICR Depth
CICR Depth1080
sacks cmt on top.withCIBP #5: Depth
sacks cmt on top.withsacks cmt on top. CIPB #4: Depth2with5000CIBP #3: Depth
Set sacks in mouse holeSetsacks in rat hole
NoYesAbove Ground Dry-Hole Marker:Cut four feet below ground level, weld on plate
Set sacks at surface
ft.ft. tosacks half in. half out surface casing fromSet
sacks. Leave at least 100 ft. in casingft. withPerforate and squeeze at
sacks. Leave at least 100 ft. in casing390ft. with1020Perforate and squeeze at
sacks. Leave at least 100 ft. in casing110ft. withPerforate and squeeze at 1300
ft. ft. tosks cmt fromSet
ft. ft. tosks cmt fromSet
ft. ft. tosks cmt fromSet
ft. ft. tosks cmt fromSet
ft. ft. tosks cmt fromSet
sacks cmt on top.7150 with 2sacks cmt on top. CIPB #2: Depth2with7850CIBP #1: Depth
Plug Type:
NOTE: Two(2) sacks cement
required on all CIBPs.
Plugging Procedure for Intent and Subsequent Report
Status
VISU0970SURF 12+1/4 8+5/8 24 970 285
CBL6,6508,0821ST 7+7/8 4+1/2 11.6 8,082 210
CBL1,3255,140Stage Tool 5,092 500
Casing Type Size of Hole Size of Casing Weight Per Foot Setting Depth Sacks Cement Cement TopCement Bot
Jacobson, Eric
Based on the information provided herein, this Well Abandonment Report (Form 6) complies with COGCC Rules and applicable
orders and is hereby approved.
COGCC Approved:Date:2/18/2020
I hereby certify all statements made in this form are, to the best of my knowledge, true, correct, and complete.
Signed:Print Name:Jennifer Thomas
Title:Regulatory Analyst Date:2/13/2020 Email:rscdjpostdrill@anadarko.com
CONDITIONS OF APPROVAL, IF ANY:
Page 2 of 4Date Run: 2/18/2020 Doc [#402312324] Well Name: ADAM FARM 8-4
COA Type Description
Added CIBP #3 at 5000' with 2 sacks on top. Operator concurs.
WITH KNOWN BRADENHEAD PRESSURE
The plug at 1300' needs to be placed and have an 8 hour WOC to assure that all fluid
migration has been stopped. If that doesn¶t isolate the flow, additional attempts in front
of the surface shoe plug will need to be attempted. Other downhole potential squeeze
opportunities may need to be looked at before the 1020' plug.
Prior to starting plugging operations a bradenhead test shall be performed if there has
not been a reported bradenhead test within the 60 days immediately preceding the start
of plugging operations.
1) If, before opening the bradenhead valve, the beginning pressure is greater than 25
psi, sampling is required.
2) If pressure remains at the conclusion of the test, or if any liquids were present during
the test, sampling is required.
The Form 17 shall be submitted within 10 days of the test. Sampling shall comply with
Operator Guidance - Bradenhead Testing and Reporting Instructions. If samples are
collected, copies of all final laboratory analytical results shall be provided to the COGCC
within three (3) months of collecting the samples.
If there is a need for sampling, contact COGCC engineering for verification of plugging
procedure.
1) Provide 48 hour notice of plugging MIRU via electronic Form 42.
2) Prior to placing the 1020' plug: verify that all fluid migration (liquid or gas) has been
eliminated. If evidence of fluid migration or pressure remains, contact COGCC Engineer
for an update to plugging orders.
3) After isolation has been verified, pump plug and displace. If cement is not circulated
to surface, shut-in, WOC 4 hours then tag plug ±must be at 920' or shallower and
provide 10 sack plug at surface.
4) Leave at least 100¶of cement in the wellbore for each plug.
5) Properly abandon on-location flowlines as per Rule 1105. File electronic Form 42
once abandonment is complete. Within 30 days of an operator completing
abandonment requirements for an off-location flowline or crude oil transfer line, the
operator must submit a Flowline Report, Form 44.
6) With the Form 6 SRA operator must provide written documentation which positively
affirms each COA has been addressed.
7) After placing the shallowest hydrocarbon isolating plug (7150'), operator must wait a
sufficient time to confirm static conditions. If at any time after placing this plug there is
evidence of pressure or of fluid migration, contact COGCC engineering before
continuing operations.
Operator shall implement measures to control venting, to protect health and safety, and
to ensure that vapors and odors from well plugging operations do not constitute a
nuisance or hazard to public welfare.
Attachment Check List
Att Doc Num Name
402312324 WELL ABANDONMENT REPORT (INTENT)
402312341 PROPOSED PLUGGING PROCEDURE
402312343 WELLBORE DIAGRAM
402314968 FORM 6 INTENT SUBMITTED
Total Attach: 4 Files
Page 3 of 4Date Run: 2/18/2020 Doc [#402312324] Well Name: ADAM FARM 8-4
User Group Comment Comment Date
Engineer Well file verification not completed prior to approval of NOIA.02/14/2020
Engineer Deepest Water Well within 1 Mile ±700'
SB5 Base of Fox Hills - N/A
Bradenhead test on 6/5/2019 had 31 psi.
02/14/2020
Permit -Confirmed as-drilled well location.
-No other forms in process.
-Production reporting up-to-date.
-Confirmed productive intervals docnum: 2510650.
-Reviewed WBD and procedure.
-Pass.
02/13/2020
Total: 3 comment(s)
General Comments
Page 4 of 4Date Run: 2/18/2020 Doc [#402312324] Well Name: ADAM FARM 8-4
API: 05-123-30568 ELEVATION: 4899 QTRQTR:SWNE
WELL NAME: ADAM FARM 8-4 GROUND LEVEL: 4884 SEC:4
COUNTY:WELD MD:8095 TWN:2N
LATITUDE:40.1712343 PBMD:8046 RNG:68W
LONGITUDE:-105.0040314 CREATED BY:N. ROSENHAGEN
DATE:February 12, 2020
Existing DATUM: RKB Proposed
390 sx
1.23 yld/AGM
15.8 ppg
1080'
110 sx
1.23 yld/AGM
2 sx
7150'
Existing Cement
2 sx New CICR
7850'Existing CICR
New CIBP
Existing CIBP
New Cement
Sand Plug
Existing Mud
Engineer: Nick Rosenhagen
Cell Phone Number: 303-345-7721
PLUG and ABANDONMENT PROCEDURE
ADAM FARM 8-4 API: 05-123-30568
Description
1. Provide 48-hour notice to COGCC prior to rig up per request on approved Form 6 (e.g. call field
coordinator, submit Form 42, etc.). Notify Automation Removal Group at least 24 hours prior to rig
move. Request they catch and remove plunger, isolate production equipment, and remove any
automation prior to rig MIRU.
2. MIRU Slickline. Pull production equipment and tag bottom. Record tag depth in Open Wells. Directional
Survey was run on 06/28/17. RDMO Slickline.
3. Prepare location for base beam equipped rig. Install perimeter fence as needed.
4. COA: Verify Form 17 (State Bradenhead Test) has been run within 60 days of RU. If Form 17 required
sampling, contact Engineering to verify plugging orders before beginning P&A operations.
5. Upon RU, check and record bradenhead pressure. If bradenhead valve is not accessible, re-plumb so
that valve is above GL. Blow down bradenhead and re-check pressure the next day. Repeat until
pressure stays at 0 psi.
6. Refer to BOP testing guidelines, fluid barrier management, and tripping best practices as applicable. All
wireline operations will need a flanged changeover, WL BOP, Lubricator with an ID to fit the largest OD
of the toolstring, and a packoff. Please contact foreman to discuss arrangement of stack, or alternate
plan. Contact your foremen with any questions regarding standard operating procedures or any
potential deviations.
7. MIRU WO rig. Kill well as necessary using biocide treated fresh water. Verify BOP and wellhead rating,
inspect for appropriate API standards, pressure test BOP according to BOP testing guidelines. ND WH.
NU BOP. Unland tbg using unlanding joint and LD.
8. Once well has been killed, pump an additional 200bbls of water to ensure wellbore is clear of gas. Must
maintain full column of fluid or constant pump rate to keep gas out until top perforations are covered
with a cast iron bridge plug.
9. TOOH and SB 1080' of 2-3/8" tbg. LD remaining 2-3/8" tbg.
10. MIRU WL. PU and RIH with (4-1/2", 11.6#) gauge ring to 7860'. POOH.
11. PU and RIH with (4-1/2", 11.6#) CIBP and set at +/- 7850' (collars at 7827' & 7870'). POOH. RIH and
dump 2 sx cement on CIBP. POOH.
12. PU and RIH with (4-1/2", 11.6#) CIBP and set at +/- 7150' (collars at 7139' & 7182'). POOH.
13. Top fill hole with biocide treated fresh water and circulate all gas out of well. PT CIBP to 500 psi for 15
minutes. A good PT has less than 10% loss in pressure and stabilization at the end of the test. Test can
be extended longer in time if need be. Contact Foreman or Engineer to confirm proceeding after
pressure test.
14. RIH and dump 2 sx of cement on top of CIBP. POOH.
15. COA: Confirm and document static conditions in the well before placing the Sussex plug. If there is
evidence of pressure or fluid migration at any time after placing the Niobrara plug, contact Engineering.
16. Run CCL/GR/CBL/VDL log from +/- 2000' to surface to confirm squeeze location. Run one pass with 500
psi on casing. Future operations may change depending on CBL results.
17. Forward logs to engineering and in addition to the normal handling of logs/job summaries, email copies
of all cement job logs/job summaries and invoices to DJVendors@anadarko.com within 24 hours of job
completion. Note that squeeze hole locations and cement volumes may vary depending on CBL results.
18. PU and RIH with one 4' 3-1/8" perf gun with 4 spf, 120° phasing, and 0.5 EHD. Shoot 4' of squeeze holes
at 1300'. POOH.
19. Establish circulation down production casing out the surface casing with fresh water and several sweeps
of mud thinner with the rig pump. Pump at least two hole volumes (146 bbl) or until returns are clean. If
unable to gain circulation, contact Foreman to discuss reverse circulation. Note: start with rig pump
FIRST.
20. If rig pump cannot pump at 6bpm, use cement truck for this step. Start at 1.5 bpm and slowly STEP up
to maintain a minimum of 6 bpm with fresh water and surfactant during the remainder of circulation to
promote hole cleaning and residual gas removal.
21. PU and RIH with one 4' 3-1/8" perf gun with 4 spf, 120° phasing, and 0.5 EHD. Shoot 4' of squeeze holes
at 1020'. POOH. RDMO WL.
22. PU and TIH with (4.5'') CICR on 2.375'' tbg. Set CICR at 1080'. Close bradenhead. Pump cement down
tubing and out the production casing x tubing annulus.
23. Note: ensure rig crew is ready to pull tubing as soon as cement is done pumping to prevent stuck tubing.
24. MIRU Cementers. Pump 20 bbl pre-flush. Pump Bradenhead Circulation Plug: 110 sx (25 bbls or 136
cuft) Class G, assuming 15.8 ppg & 1.23 yld with 0.40% Latex, 2% Calcium Chloride, and 4% Gypsum. Mix
water must be 70°F (may have to bring out cold water to dilute heated water). Volume is based on 60'
in 4.5'' production casing on top of the CICR, 220' in 4.5'' production casing under the CICR, and 280' in
4.5'' production casing x 7.875'' open hole with 60% excess. This plug is designed to cover 1300' - 1020'.
Collect wet and dry samples of cement to be left on rig. RDMO Cementers. Notify engineering if
circulation is ever lost during the job.
25. Pull out of cement at a rate of 1 jt/min. Displace cement wtih 1 bbl of fresh water. TOOH to 1020'.
Attempt to reverse circulate down the production casing and up tubing through stinger with 12 ppg
mud. If circulation cannot be achieved, forward circulate down tubing, up production casing with 12 ppg
mud to ensure no cement is left in the tbg and to clean up top perforation holes. TOOH all 2.375'' tbg
while continuing to fill hole with mud. Note: you will need at least 16 bbl 12 ppg mud to fill hole from
estimated TOC to surface while TOOH.
26. Establish circulation down casing and up bradenhead with 12 ppg mud to ensure top perforations are
able to circulate before SDFN. WOC 8 hours.
27. COA: Verify and document that all pressure and fluid migration has been eliminated prior to placing the
SC shoe plug at 1020'. If there is evidence of pressure or fluid migration, contact Engineering.
28. Open bradenhead - circulate through both surface valves if applicable to the wellhead for water/mud
circulation and cement.
29. ND BOP. Connect B1 swedge to 4.5'' casing.
30. MIRU Cementers. Pump 20 bbl pre-flush. Pump surface circulation plug: 390 sx (86 bbls or 480 cuft)
Class G, assuming 15.8 ppg & 1.23 yld with 0.40% Latex, 2% Calcium Chloride, and 4% Gypsum. Mix
water must be 70°F (may have to bring out cold water to dilute heated water). Volume is based on
1020' in 4.5'' production casing with no excess, 50' in 4.5'' production casing x 7.875 open hole annulus
with 100% excess, and 970' in 4.5'' production casing x 8-5/8'' surface casing annulus with no excess plus
an additional 100 sx. This plug is designed to cover 1020' - 0'. Excess is calculated into the job - pump
cement until you receive 15.8 ppg cement on the backside. Collect wet and dry samples of cement to be
left on rig. RDMO Cementers. Notify engineering if circulation is ever lost during the job.
31. If returns are not circulated to surface, WOC 4 hours and tag. Cement must be 80' or shallower. RDMO
WO rig.
32. Instruct cementing and wireline contractors to e-mail copies of all job logs/job summaries to
rscDJVendors@anadarko.com within 24 hours of completion of the job.
33. Supervisor submit paper copies of all invoices, logs, and reports to VWP Engineering Specialist.
34. Excavation crew to notify One Call to clear excavation area around wellhead and for flow lines.
35. Excavate hole around surface casing enough to allow welder to cut casing a minimum 5’ below ground
level.
36. Welder cut casing minimum 5' below ground level.
37. Spot weld on steel marker plate. Marker should contain Well name, Well number, legal location (1/4
1/4 descriptor) and API number.
38. Obtain GPS location data as per COGCC Rule 215 and send to rscDJVendors@anadarko.com.
39. Properly abandon flow lines per Rule 1103. File electronic Form 42 once abandonment is complete.
40. Back fill hole with fill. Clean location, and level.
41. Submit Form 6 to COGCC ensuring to provide 'As performed' WBD identifying operations completed.