HomeMy WebLinkAbout 19-93 Change Order No. 2 to Agreement with Communication Construction and Engineering Inc. for Police Station Fiber Optic Line ProjectRESOLUTION 19-93
A RESOLUTION OF THE BOARD OF TRUSTEES OF THE TOWN OF
FIRESTONE, COLORADO, APPROVING CHANGE ORDER NO.2 TO THE
AGREEMENT BETWEEN THE TOWN OF FIRESTONE AND
COMMUNICATION CONSTRUCTION & ENGINEERING, INC.,
REGARDING THE POLICE STATION FIBER OPTIC LINE PROJECT
WHEREAS, the Town of Firestone ("Town") entered into an Agreement with
Communication Construction & Engineering Inc ("Contractor") for the installation of
dedicated fiber intranet between Town Hall and the new Police Department and Municipal
Court ("Police Station Fiber Optic Line Project"); and
WHEREAS, the Town has determined that it would be advantageous to the Town's
operations to expand the Project to include dedicated fiber intranet to the Town's Public Works
Facility; and
WHEREAS, Contractor is able to perform the required Project work of installing
conduit and single mode fiber from the new Police Department to the Public Works Facility.
NOW, THEREFORE, BE IT RESOLVED BY THE BOARD OF TRUSTEES OF THE
TOWN OF FIRESTONE, COLORADO:
The Change Order No. 2 to the Town of Firestone and Communication Construction &
Engineering, Inc., Agreement regarding the Police Station Fiber Optic Line Project is approved
in substantially the same form as the copy attached hereto and made a part of this resolution, and
the Mayor is authorized to execute the Change Order on behalf of the Town.
INTRODUCED, READ AND ADOPTED this 9th day of October, 2019.
d OF F RESTOI`
r
Sind r, Mayor
ATTEST:
Leah Vanarsdall, Town Clerk
AS TO FORM:
WilliariYP. yashi, Town Attorney
SECTION 00941
CHANGE ORDER
No. 2
Date of Issuance: October 10, 2019 Effective Date:
Project: Police Station Fiber Optic Line Owner. Town of Firestone Owner's Contract No.:
Project 1000-450600-931-800
Contract: Date of Contract:
Construction Services July 10, 2019
Contractor: Engineer's Project No.: 0668.0189.02
Communication Construction and Engineering, Inc.
The Contract Documents are modified as follows upon execution of this Change Order:
Description:
See attached detail
Attachments (list documents supporting change):
Descriptions
CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES:
Original Contract Price: Original Contract Times: ❑ Working days ❑ Calendar days
Substantial completion (days or date): September 23, 2019
$1979674.07 Ready for final payment (days or date): October 7, 2019
[Increase] [Decrease] from previously approved Change
Orders No. 0 to No. 1:
$2 575.00
Contract Price prior to this Change Order:
$ 200 249.07
[Increase] [Decrease] of this Change Order:
$145,282.00
Contract Price incorporating this Change Order:
(Z
345.531.07
RECOMMENDED:
By: By:
Engineer (Authorized Signature)
)
ate: Date:
Approved by Funding Agency (if applicable):
[Increase] [Decrease] from previously approved Change Orders
No. 0 to No. 1:
Substantial completion (days):
Ready for final payment (days):
Contract Times prior to this Change Order:
Substantial completion (days or date): September 23 2019
Ready for final payment (days or date): October 7. 2019
[Increase] [Decrease] of this Change Order:
Substantial completion (days or date): TBD
Ready for final payment (days or date): TBD
Contract Times with all approved Change Orders:
Substantial completion (days or date): TBD
Ready for final payment (days or date): TBD
ACCEPTED:
re) Contractor (Authorized Signature)
Date:
Date:
EJCDC C-941 Change Order
Prepared by the Engineers Joint Contract Documents Committee and endorsed by the Construction Specifications Institute.
00941-1 of 3
DESCRIPTION:
Item No. 1 — REVISED & ADDITIONAL WORK QUANTITIES — NET CHANGE = $145,282.00
In order to install additional fiber optic line from the handhole at the intersection Of Pine Cone Avenue
to the Town of Firestone Public Works Building to provide a dedicated fiber optic connection between
the Town Hall and the Public Works Building the following quantities have been increased and/or
additional quantities have been added. Items 24, 26, 28, & 29 are listed as add items due to an
increase or decrease in unit price since the original bid.
REVISED Item 5. ASPHALT /CONCRETE SAWCUT
Quantity = 3000 (Increase 100 SF)
Unit =SF
Unit Price = $5.00
Net Change = $ 500.00
REVISED Item 10. DIRECTIONAL BORE (EROSION CONTROL,
RESEED & MULCH)
Quantity = 16,855 (Increase 8,200 LF)
Unit = LF
Unit Price = $12.30
Net Change = $ 100,860.00
REVISED Item 12. 2" CONDUIT (BORE)
Quantity = 16,855 (Increase 8,200 LF)
Unit = LF
Unit Price = $0.94
Net Change = $ 7,708.00
REVISED Item 13. TRACER WIRE
Quantity = 21,400 (Increase 8,500 LF)
Unit = LF
Unit Price = $ 0.22
Net Change = $ 11870400
REVISED Item 15. FLEXIBLE UTILITY MARKERS
Quantity = 26 (Increase of 9)
Unit = EA
Unit Price = $ 45.00
Net Change = $ 405.00
ADD Item 24. MOBILIZATION
Quantity = 1
Unit = LS
Unit Price = $ 750.00
Net Change = $ 750.00
ADD Item 25, EXCAVATE CONDUIT AND SPLICE
Quantity = 10
Unit = EA
Unit Price = $ 250.00
Net Change = $ 2500600
TOPSOIL STOCKPILE &PLACE,
EJCDC C-941 Change Order
Prepared by the Engineers Joint Contract Documents Committee and endorsed by the Construction Specifications Institute.
00941-2 of 3
ADD Item 26, 24x36 HANDHOLE
Quantity = 9
Unit = EA
Unit Price = $ 801.00
Net Change = $ 7,209.00
ADD Item 27. PROVIDE AND PLACE MULE TAPE
Quantity = 8,500
Unit = LF
Unit Price = $ 0.30
Net Change = $ 2,550.00
ADD Item 28. FIBER OPTIC CABLE (12-STRAND SINGLE MODE)
Quantity = 10,000
Unit = LF
Unit Price = $ 1.72
Net Change = $ 17,200.00
ADD Item 29 TRAFFIC CONTROL
Quantity = 8
Unit =EA
Unit Price = $ 400.00
Net Change = $ 3,200.00
ADD Item 30. CONSTRUCT 2" BUILDING ENTRANCE
Quantity = 1
Unit =EA
Unit Price = $ 530.00
Net Change = $ 530.00
END OF SECTION
EJCDC C-941 Change Order
Prepared by the Engineers Joint Contract Documents Committee and endorsed by the Construction Specifications Institute.
00941-3 of 3
BASE BID
FIRESTONE POLICE STATION FIBER OPTIC LINE
DESCRIPTION UNIT
REMOVAL & REPLACEMENT
CONTRACT
QUANTITYITEM
UNIT PRICE
TOTAL PRICE
1
ASPHALT/CONCRETE SAW-CUT(CO#i)
LF
0
$10.00
$0.00
2
ASPHALT REMOVAL & REPLACEMENT
SY
6
$80.00
$480.00
3
CONCRETE REMOVAL & REPLACEMENT(CO#1)
SF
0
$25.00
$0.00
4
GRAVEL REMOVAL & REPLACEMENT(CO#1)
SY
1 0
$55.00
$0.00
5
LANDSCAPE REMOVAL & REPLACEMENT(CO#2)
SF
300
$5.00
$1,500.00
6
IRRIGATION REMOVAL & REPLACEMENT
HR
10
$75.00
$750.00
SUBTOTAL
$2 730.00
EROSION CONTROL& EARTHWORK
7
VEHICLE TRACKING CONTROL PAD
EA
2
$450900
$900600
8
BORE PITS (EROSION CONTROL, TOPSOIL STOCKPILE & PLACE, RESEED & MULCH)
EA
5
$250900
$1,250.00
9
TRENCH/PLOW (EROSION CONTROL, TOPSOIL STOCKPILE & PLACE, RESEED & MULCH)(CO#1)
LF
31290
$8.80
$281952.00
10
DIRECTIONAL BORE (EROSION CONTROL, TOPSOIL STOCKPILE & PLACE, RESEED & MULCH)(CO#1)(CO#2)
LF
16,855
$12.30
$207,316,50
SUBTOTAL
$238,418.50
UTILITIES
11
2" CONDUIT (TRENCH/PLOW)(CO#1)
LF
31290
$0.94
$31092.60
12
2" CONDUIT (DIRECTIONAL BORE)(CO#1)(CO#2)
LF
16,855
$0.94
$151843.70
13
TRACER WIRE (CO#2)
LF
21,400
$0.22
$4,708.00
14
24" X36" HANDHOLE (1,000 FOOT SPACING +/-)(CO#1)
EA
17
$590000
$10,030.00
15
FLEXIBLE UTILITY MARKERS (AT COMMUNICATIONS BOXES)(CO#1)(CO#2)
EA
26
$45.00
$11170.00
16
FIBER OPTIC CABLE (12-STRAND SINGLE MODE)(SEE ITEM #22)
LF
0
$1.30
$0.00
17
TERMINATION POINTS
EA
2
$1,447.25
$21894.50
SUBTOTAL
$37,738.80
MISCELLANEOUS
18JTLRAFFLICONTROL
LS
1
$2,437.50
$2,437.50
19ION
(5%)
LS
1
$7,419.27
$7,419.27
SUBTOTAL
$%856.77
20
4" CONDUIT (TRENCH/PLOW)(ALT. NOT APPROVED)
LF
0
$11.35
$0.00
21
4" CONDUIT (DIRECTIONAL BORE)(ALT. NOT APPROVED)
LF
0
$19.85
$0.00
22
FIBER OPTIC CABLE (24-STRAND SINGLE MODE)(ALT, APPROVED)
LF
12,900
$1.67
$211543.00
23
CONDUIT REPAIR (CO#1)
EA
1
$11305.00
$1,305.00
24
MOBILIZATION (CO#2)
LS
1
$750.00
$750.00
25
EXCAVATE CONDUIT AND SPLICE(CO#2)
EA
10
$250.00
$2,500.00
26
24" X36" HANDHOLE (1,000 FOOT SPACING +/-)(CO#2)
EA
9
$801600
$7,209.00
27
PROVIDE AND PLACE MULE TAPE(CO#2)
LF
81500
$0.30
$21550.00
28
FIBER OPTIC CABLE (12-STRAND SINGLE MODE)(CO#2)
LF
10,000
$1.72
$171200.00
29
TRAFFIC CONTROL (CO#2)
EA
8
$400.00
$3,200.00
30
CONSTRUCT 2" BUILDING ENTRANCE TO INCLUDE CORE BORE AND NEMA BOX
EA
1
$530.00
$530.00
SUBTOTAL
$561787.00
CONSTRUCTION COST TOTAL CO#1 CO#2 $345,531.07
1of1