HomeMy WebLinkAbout22-73 Approving Change in Order no. 1 Brannan Sand Gravel Company Contract 06-08-2022RESOLUTION NO. 22-73
A RESOLUTION OF THE BOARD OF TRUSTEES OF TIiF TOWN OF
FIRESTONE. COLORADO, APPROVING CHANGE ORDER NO. 1 TO
THE CONSTRUCTION CONTRACT BETWEEN THE TOWN OF
FIRESTONE AND BRANNAN SAND AND GRAVEL COMPANY FOR THE
V1ILL AND OVERLAY PAVING PROJECT FOR PORTIONS OF
FIRESTONE AND COLORADO BOULEVARDS
WHEREAS, on March 23, 2022, the Town of Firestone ("Town") and Brannan Sand and
Gravel Company ("Contractor") entered into a Constriction Contract for mill and overlay work
for both lanes o; Firestone Blvd from Oak Meadows Blvd to Cimarron Str:et and for both lanes
of Colorado Blvd from Cimarron Street to Oak i-.4eadows Blvd; and
WHEREAS, prior to tine cornunerncement ofwork Town staff determined that an additional
area of Firestone Blvd east of Oak Meadows Blvd was also in need of mill and overlay services;
and
WHEREAS, as Contractor is on -site, staff finds that it would be beneficial in terms of
efficiency and cost to have Contractor perform the additional mill and overlay work and thus
recommends approval of Change Order No. 1.
NOW, THEREFORE, BE IT RESOLVED BY THE BOARD OF TRUSTEES OF THE
TOWN OF FIRESTONE, COLORADO:
Change Order No. 1 to the Construction Contract between the Town of Firestone and
Brannan Sand and Gravel Company, is approved in substantially the same form as the copy
attached hereto and made a part of this resolution, and the Mayor is authorized to execute
Change Order No. 1 on behalf of the Town.
INTRODUCED, READ, AND ADOPTED this 8t1A day of June, 2022.
,COLORADO
Alan Peterson, Mayor
ATTEST:
APPROVED
Date of Issuance; -
2,0zk
SECTION UUU41
CHANGE ORDER
Effective Date: June 8, 2022
Project: Pavement Maintenance (S2022- Owner: Town of Firestone
9228)
Mill and overlay of Firestone Blvd and Colorado Blvd
Contract No.:
Date of Contract: March 23, 2U22
Contractor; Engineer's Project No,: NIA
Brannan Sand and Gravel Company
The Contract Documents are modified as follows upon execution of this Change Order:
Description:
Mill and overlay an additional 5 250 Sq-yds on Firestone Blvd From Oak Meadows Blvd to approximately 700 Ft East.
See attached
Attachments (list documents supporting change):
Mill and overlay of an additional 5,250 Sq-yds on Firestone Blvd From Oak Meadows Blvd to approximately 700 ft east
Graphic Exhibit
IN CONTRACT PRICE:
Original Contract Price:
$670 008.23
[Increase] [Decrease] from previously approved Change
Orders No. 0 to No. 0:
Contract Price prior to this Change Order:
$670 008.23
[Increase] of this Change Order:
$104 750.00
Contract Price incorporating this Change Order:
GE IN CONTRACT TIMES:
Original Contracf Times: Working days ❑Calendar days
Substantial completion (days or date): 120 days
Ready for final payment (days or date): Upon completion
[Increase] [Decrease] from previously approved Change Orders
No. 0 to No. 0:
Substantial completion (days): 0
y for payment (days
Readfinal ): 0
Contract Times prior to this Change Order:
Substantial completion (days or date): 120 days
Ready for final payment (days or date): Upon completion
[Increase] [Decrease] of this Change Order:
Substantial completion (days or date): +0 days
Ready for final payment (days or date): +0 days
Contract Times with all approved Change Orders:
Substantial completion (days or date): 120 days
$774 758.23 Ready for final payment (days or date): Upon completion
RECOMMENDED: