HomeMy WebLinkAbout22-84 Approving change in Order No. 2 Brannan Sand & Gravel Company Mill & Overlay Paving Project 07-13-2022RESOLUTION NO. 22-84
A RESOLUTION OF THE BOARD OF TRUSTEES OF THE TOWN OF
FIRESTONE, COLORADO, APPROVING CHANGE ORDER NO.2 TO
THE CONSTRUCTION CONTRACT BETWEEN THE TOWN OF
FIRESTONE AND BRANNAN SAND AND GRAVEL COMPANY FOR THE
MILL AND OVERLAY PAVING PROJECT FOR PORTIONS OF
FIRESTONE AND COLORADO BOULEVARDS
WHEREAS, on March 23, 2022, the Town of Firestone ("Town") and Brannan Sand and
Gravel Company ("Contractor") entered into a Construction Contract for mill and overlay work
for both lanes of Firestone Blvd from Oak Meadows Blvd to Cimarron Street and for both lanes
of Colorado Blvd from Cimarron Street to Oak Meadows Blvd; and
WHEREAS, after the commencement of work Town staff determined that an additional
area of Colorado Blvd south of Firestone Blvd was also in need of mill and overlay services; and
WHEREAS, because the Contractor was already on -site it was beneficial in terms of cost
for the Town to have Contractor perform the additional work which was approved by the Town's
approval of Change Order No.1 which occurred on June 8, 2022; and
WHEREAS, the Town now finds that rather than proceed with the proposed crack -seal
work for Colorado Blvd from Cimarron St to Sable Ave and Colorado Blvd from Sable Ave to
Pine Cone Ave it would be more beneficial in terms of the quality and effectiveness of the
improvements to have the locations milled and overlayed as set forth in Change Order No. 2.
NOW, THEREFORE, BE IT RESOLVED BY THE BOARD OF TRUSTEES OF THE
TOWN OF FIRESTONE, COLORADO:
Change Order No. 2 to the Constiuction Contract between the Town of Firestone and
Brannan all and Gravel Company, is approved in substantially the same form as the copy
attached hereto and made a part of this resolution, and the Mayor is authorized to execute
Change Order No. 2 on behalf of the Town.
INTRODUCED, READ,
ATTEST:
J sj a Koenig,
APPROVED AS TO FO
OPTED this 13th day of July, 2022.
�5,.••,� •.,�0�TOWN OF FIRES
�rr4
s
Drew Alan Petersc
. ��
COLORADO
Mayor
SECTION 00941
CHANGE ORDER
No. 2
Date of Issuance: �� - Effective Date: July 13, 2022
Project: Pavement Maintenance -Mill and Owner: Town of Firestone Owner's Contract No.: S2022-9228
Overlay (S2022-9228)
Contract: Date of Contract: March 23, 2022
Mill and overlay of Colorado Blvd from Cimmeron St. to Pine cone Ave.
Contractor:
Brannan Sand and Gravel Company
neer's Project No.: N/A
The Contract Documents are modified as follows upon execution of this Change Order:
Mill and overlay of Colorado Blvd. From Cimmeron St. to Pine Cone Ave approximately 51,650 Sq-yds.
See attached
Attachments (list documents supporting change);
Mill and overlay of Colorado Blvd, from Cimmeron St. to Pine Cone Ave Approximately 51,650 Sq-yds.
Graphic Exhibit
CHAN
Original Contract Price:
$670 008.23
PRI
[Increase] from previously approved Change Orders No.
1 to No. 1:
$104 750.00
Contract Price prior to this Change Order:
$774 758.23
[Increase] of this Change Order:
$752 408.43
Contract Price incorporating this Change Order:
$1.527.166.66
RECOMMENDED: ACCI
B . BY' �
P liccWorks (Authorized Signature) C
Date: O ���� a� Date:
CHANGE IN CONTRACT TIMES:
Original Contract Times: ®Working days ❑Calendar days
Substantial completion (days or date): 120 days
Ready for final payment (days or date): Upon completion
[Increase] [Decrease] from previously approved Change Orders
No. 1 to No. 1:
Substantial completion (days): 0
Ready for final payment (days): 0
Contract Times prior to this Change Order:
Substantial completion (days or date): 120
days
Ready for final payment (days
or date):
Upon
completion
[Increase] [Decrease] of this Change Order:
Substantial completion (days or date): +0 days
Ready for final payment (days or date): +0 days
Contract Times with all approved Change Orders:
Substantial completion (days or date):
120
days
Ready for final payr�Q�date):
Upon
completion
(Authorized
TOWN
Q onlFa6tor (Authorized Signature)